Skip to content

BMP Criteria Comparison

Compare the actual practice and configuration before comparing numbers. The 2023 and 2026 headings identify collections; a chapter may retain an earlier publication date. Both Chapter 12 copies are dated March 2024, so they do not establish the exact July 2023 historical text.

The January 2026 volumetric-reduction framework adds an objective. Existing reuse, infiltration and evapotranspiration processes already occur in the earlier practice chapters. See Chapter 14.

Chapter eligibility tables describe the ordinary pathway. See GI requirements for conditional exceptions, including qualifying public transportation projects.

Bioretention

Criterion Earlier chapter collection 2026 chapter collection
Contributing drainage area Maximum 2.5 acres contributory drainage area PDF Maximum 2.5 acres contributory drainage area PDF
Maximum ponding depth WQDS maximum 12 in flat-bottom; 18 in at down-gradient end of sloped-bottom system (maximum longitudinal slope 10%) PDF WQDS maximum 12 in flat-bottom; 18 in at down-gradient end of sloped-bottom system (maximum longitudinal slope 10%) PDF
Typical ponding depth No separately specified typical depth; use the configuration-specific maxima PDF No separately specified typical depth; use the configuration-specific maxima PDF
Engineered media depth 80% TSS: minimum 18 in with terrestrial forested vegetation or 24 in with site-tolerant grasses; 90% TSS: minimum 24 in with terrestrial forested vegetation PDF 80% TSS: minimum 18 in with terrestrial forested vegetation or 24 in with site-tolerant grasses; 90% TSS: minimum 24 in with terrestrial forested vegetation PDF
Filter media composition 85–95% sand by volume (no more than 25% of sand fine/very fine); no more than 15% silt/clay including 2–5% clay; amend with 3–7% organics by weight PDF 85–95% sand by volume (no more than 25% of sand fine/very fine); no more than 15% silt/clay including 2–5% clay; amend with 3–7% organics by weight PDF
Drawdown time Maximum 72 hours; 24 hours recommended where pedestrians can access standing water PDF Maximum 72 hours; 24 hours recommended where pedestrians can access standing water PDF
Underdrain required when Select the configuration for site conditions and objectives; underdrained systems cannot meet recharge requirements or include exfiltration in quantity routing PDF Select the configuration for site conditions and objectives; underdrained systems cannot meet recharge requirements or include exfiltration in quantity routing PDF
SHWT separation Underdrained: at least 1 ft below gravel bottom, with specified impervious-structure exception. Infiltrating: Example 3 applies 2 ft minimum below lowest soil-bed bottom PDF Underdrained: at least 1 ft below gravel bottom, with specified impervious-structure exception. Infiltrating: Example 3 applies 2 ft minimum below lowest soil-bed bottom PDF
K_design calculation min(slowest eligible tested rate / 2, 10 in/hr), subject to practice criteria and hydraulic-impact assessment PDF min(slowest eligible tested rate / 2, 10 in/hr), subject to practice criteria and hydraulic-impact assessment PDF
Pretreatment required Required when exfiltration is included in routing the larger design storms; no adopted standalone TSS credit for the forebay PDF Required when exfiltration is included in routing the larger design storms; no adopted standalone TSS credit for the forebay PDF

Dry Well

Criterion Earlier chapter collection 2026 chapter collection
Minimum subsoil design permeability Minimum design 0.5 in/hr; governing tested minimum 1.0 in/hr before factor of safety 2 PDF Minimum design 0.5 in/hr; governing tested minimum 1.0 in/hr before factor of safety 2 PDF
SHWT separation At least 2 ft from dry-well bottom to SHWT and bedrock PDF At least 2 ft from dry-well bottom to SHWT and bedrock PDF
Drawdown time Maximum 72 hours PDF Maximum 72 hours PDF
Foundation setback Setback established by local ordinance or applicable review agency; no universal 10 ft criterion in Chapter 9.2 PDF Setback established by local ordinance or applicable review agency; no universal 10 ft criterion in Chapter 9.2 PDF
Septic system setback Setback established by local ordinance or applicable review agency; no universal 10 ft criterion in Chapter 9.2 PDF Setback established by local ordinance or applicable review agency; no universal 10 ft criterion in Chapter 9.2 PDF
Required infiltration test method Preconstruction methods per Chapter 12; convert percolation to conductivity. Fractured-bedrock basin flooding is pass/fail. Postconstruction methods must not require a hole in the soil layer PDF Preconstruction methods per Chapter 12; convert percolation to conductivity. Fractured-bedrock basin flooding is pass/fail. Postconstruction methods must not require a hole in the soil layer PDF
K_design calculation min(slowest eligible tested rate / 2, 10 in/hr), subject to practice criteria and hydraulic-impact assessment PDF min(slowest eligible tested rate / 2, 10 in/hr), subject to practice criteria and hydraulic-impact assessment PDF

Cistern

Criterion Earlier chapter collection 2026 chapter collection
Storage capacity / sizing method WQDS volume without overflow; restore capacity within 72 hours based on lowest three-consecutive-day demand PDF WQDS volume without overflow; restore capacity within 72 hours based on lowest three-consecutive-day demand PDF
Chapter 14 volumetric reduction credit Storage and reuse retention already present in Chapter 9.1; no Chapter 14 PDF Chapter 14 adds the volumetric-reduction framework, including retention through reuse PDF

Grass Swale

Criterion Earlier chapter collection 2026 chapter collection
Maximum side slope Maximum 3H:1V; 4H:1V recommended PDF Maximum 3H:1V; 4H:1V recommended PDF
Maximum longitudinal slope Maximum 10%; below 2% requires tested rate at least 1 in/hr and SHWT separation at least 2 ft PDF Maximum 10%; below 2% requires tested rate at least 1 in/hr and SHWT separation at least 2 ft PDF

Green Roof

Criterion Earlier chapter collection 2026 chapter collection
Growing media depth (extensive) Extensive media depth 6 in or less in prose; intensive 6 in or greater; apply actual assembly criteria at overlapping boundary PDF Extensive media depth 6 in or less in prose; intensive 6 in or greater; apply actual assembly criteria at overlapping boundary PDF
Volumetric reduction credit (Ch. 14) Retention and evapotranspiration already described; other BMPs may help retain the entire WQDS PDF Chapter 14 adds volumetric framework; dry wells, cisterns, rain gardens or pervious paving are possible combinations, not a universal cistern requirement PDF

Infiltration Basin

Criterion Earlier chapter collection 2026 chapter collection
Minimum Ksat Minimum design 0.5 in/hr; tested minimum 1.0 in/hr before factor of safety 2 PDF Minimum design 0.5 in/hr; tested minimum 1.0 in/hr before factor of safety 2 PDF
SHWT separation At least 2 ft below basin bottom to SHWT PDF At least 2 ft below basin bottom to SHWT PDF
K_design calculation min(slowest eligible tested rate / 2, 10 in/hr), subject to practice criteria and hydraulic-impact assessment PDF min(slowest eligible tested rate / 2, 10 in/hr), subject to practice criteria and hydraulic-impact assessment PDF

Pervious Pavement

Criterion Earlier chapter collection 2026 chapter collection
Surface and storage porosity Specified asphalt/concrete surface porosity 15–25%; aggregate porosity 40% is an example assumption to substantiate, not a universal void ratio PDF Specified asphalt/concrete surface porosity 15–25%; aggregate porosity 40% is an example assumption to substantiate, not a universal void ratio PDF
SHWT separation SHWT or bedrock at least 1 ft below storage-bed bottom for underdrained systems; at least 2 ft for infiltrating systems PDF SHWT or bedrock at least 1 ft below storage-bed bottom for underdrained systems; at least 2 ft for infiltrating systems PDF

Rain Garden

Rain garden is a bioretention application described on Chapter 9.7 p2. Chapter 9.7.

Small Scale Sand Filter

Infiltrating GI; underdrained sand filters are excluded and belong to Chapter 11.4. Chapter 9.9.

Subsurface Gravel Wetland

Non-GI; no GI, quantity or recharge use; 90% TSS quality use requires waiver or variance. Chapter 11.5.

Tree Trench

Street trenches and enhanced/continuous tree pits are described on Chapter 9.7 p2. Separate basin designs require their own demonstrated chapter match. Chapter 9.7.

Vegetated Filter Strip

GI quality 60–80% depending on vegetation; quantity and recharge uses not allowed. Chapter 9.10.

Ch10 Large Bioretention

Criterion Earlier chapter collection 2026 chapter collection
Contributing drainage area Use Chapter 10.1 and the applicable rule eligibility; the Chapter 9.7 small-scale limit is 2.5 acres PDF Use Chapter 10.1 and the applicable rule eligibility; the Chapter 9.7 small-scale limit is 2.5 acres PDF

Constructed Wetland

GI; recharge not allowed; quality use requires waiver or variance; quantity for online systems. Chapter 10.4.

Extended Detention Ch10

Non-GI; no GI or recharge use; quality and quantity uses require waiver or variance. Existing URL does not change classification. Chapter 11.2.

Infiltration Trench

Editorial design entry point; actual configuration must meet Chapter 10.2 before its criteria or credits apply. Chapter 10.2.

Criterion Earlier chapter collection 2026 chapter collection
SHWT separation If Chapter 10.2 applies: at least 2 ft from SHWT or bedrock to lowest basin bottom; use sand-layer bottom for surface basins PDF If Chapter 10.2 applies: at least 2 ft from SHWT or bedrock to lowest basin bottom; use sand-layer bottom for surface basins PDF

Sand Filter Ch10

Infiltrating GI; recharge and quality uses require waiver or variance; quantity for online systems. Chapter 10.3.

Wet Pond Ch10

GI requires native-vegetation buffer at least 10 ft wide along at least 50% of shoreline AND retention for beneficial reuse. No recharge; quality use requires waiver or variance. Chapter 11.6 covers non-GI wet ponds. Chapter 10.5.

Blue Roof

Non-GI; quantity use requires waiver or variance; no quality or recharge use. Chapter 11.1.

Dry Detention

Detention application, not a separate chapter; use Chapter 11.2 eligibility. Chapter 11.2.

Extended Detention Ch11

Non-GI; no GI or recharge use; quality and quantity uses require waiver or variance. Chapter 11.2.

Hydrodynamic Separator

Hydrodynamic separation is a named Chapter 11.3 type. Actual certificate and configuration control eligibility. Chapter 11.3.

Manufactured Treatment Device

Chapter 11.3 covers non-GI devices; GI devices are addressed in 9.5. Actual certification and configuration control. Chapter 11.3.

Membrane System

Generic product label; no device-specific approval established. Require actual certificate and configuration before classification or credit. Chapter 11.3.

Oil Grit Separator

Generic product label; no device-specific approval established. Require actual certificate and configuration before classification or credit. Chapter 11.3.

Underground Detention

Subsurface vault, pipe and stone-bed arrangements appear in Chapter 11.2, p12; non-GI eligibility applies. Chapter 11.2.

Return to the BMP Library