GWR Review Workflow (In-House)

Internal Operating Guide · Rev 1

6-phase dual-lane operating workflow for agents and interns conducting GWR permit reviews using the Tool_GWR_Rev1 package.


Overview

The GWR review is executed in six phases, each with an agent lane (autonomous execution) and an intern lane (supervised execution). Each phase has a pass/fail checkpoint before proceeding.

Phase Name Primary Gate(s) Output
0 Problem Definition & Authority Lock G0 TCD confirmed, era locked
1 Constraints & Criteria G1, G2 Fatal constraints cleared, K_design established
2 Concept Development Architecture check BMP inventory, gate applicability matrix
3 Preliminary Design G3, G4 Storage and drain time verified
4 Detailed Design / Audit Execution G5, G6 SHWT separation + NJGRS reconstruction
5 Verification & Delivery G7 CSV export, deficiency report, review log

Phase 0 — Problem Definition & Authority Lock

Objective: Freeze the governing rule era before any calculations begin.

  • Locate the Technical Completeness Date (TCD) from the NJDEP submission.
  • Compare TCD to January 20, 2026 to determine era (2023 Legacy or 2026 REAL Rule).
  • Set the checklist header fields (project, county, era, date).
  • Review Gate G0 items.

PASS checkpoint: TCD documented, era locked, G0 items reviewed.

→ See full instructions: Toolbox/Tool_GWR_Rev1/agent_workflows/phases/phase_0_problem_definition.md


Phase 1 — Constraints & Criteria (Fail-Closed Gates)

Objective: Confirm fatal constraints are addressed and K_design is established.

  • Review Gate G1 items: HPL source areas, contamination/RAWP, pretreatment.
  • If any G1 item is FAIL: export CSV and stop. Do not proceed.
  • Review Gate G2 items: test pit logs, test method, basin flood computations, K_design.
  • Record K_design (ft/hr) = K_field / 2.0.

PASS checkpoint: All G1 items PASS or N/A; K_design value documented.

→ See full instructions: Toolbox/Tool_GWR_Rev1/agent_workflows/phases/phase_1_constraints_criteria.md


Phase 2 — Concept Development (Audit Architecture)

Objective: Calibrate the gate sequence for this project before executing math.

  • Build BMP inventory table (BMP ID, type, dimensions, elevations).
  • Confirm gate applicability (required vs N/A).
  • Run phantom storage pre-screen (void ratio 0.40 check).
  • Confirm era-specific criteria matrix.

PASS checkpoint: BMP inventory complete; gate applicability documented.

→ See full instructions: Toolbox/Tool_GWR_Rev1/agent_workflows/phases/phase_2_concept_development.md


Phase 3 — Preliminary Design (Storage & Drain Time)

Objective: Verify storage volume (G3) and drain time (G4) for each BMP.

  • Use the Storage Calculator in the checklist tool for each BMP.
  • Use the Drain Time Calculator: t = V / (A × K_design).
  • Compare computed drain time to limit (≤ 72 hr or ≤ 48 hr subsurface).

PASS checkpoint: G3 and G4 items reviewed; no deficits or over-limit drain times.

→ See full instructions: Toolbox/Tool_GWR_Rev1/agent_workflows/phases/phase_3_preliminary_design.md


Phase 4 — Detailed Design / Audit Execution (SHWT & NJGRS)

Objective: Verify SHWT separation (G5) and NJGRS recharge reconstruction (G6).

G5: - Establish SHWT elevation from boring logs. - Compute separation = d_EXC elevation − SHWT elevation. - For 2026 era: apply mound apex correction if static separation < 5 ft. - Required: effective separation ≥ 2 ft.

G6 (if NJGRS credit claimed): - Verify pre-construction cover (2026: must be "Wooded/Good"). - Verify county rainfall factor applied (2026 only). - Spot-check credited recharge volume against order-of-magnitude estimate.

PASS checkpoint: G5 and G6 items reviewed; separation documented; NJGRS inputs confirmed.

→ See full instructions: Toolbox/Tool_GWR_Rev1/agent_workflows/phases/phase_4_detailed_design.md


Phase 5 — Verification & Delivery

Objective: Final QC, export artifacts, and package handoff.

  • Review Gate G7 deliverable integrity items.
  • Run 7-point unit sanity check (volume, K_design, void ratio, SHWT cross-references).
  • Export CSV (gwr-checklist-[Project]-[Date].csv).
  • Export deficiency report PDF if any FAIL or ND items.
  • Append row to review log.

PASS checkpoint: G7 reviewed, all items have status, CSV and PDF exported, log updated.

→ See full instructions: Toolbox/Tool_GWR_Rev1/agent_workflows/phases/phase_5_verification_delivery.md


Build & Publish

To update the published tool after modifying seed files or the HTML:

cd c:\Opal_Rev1
python scripts/run_gwr_workflow.py
# Optional site rebuild:
python scripts/run_gwr_workflow.py --build-site

See scripts/run_gwr_workflow.py for all options.


System Prompt for Agent-Assisted Reviews

When using an LLM to assist with a GWR review, load the system prompt from: Toolbox/Tool_GWR_Rev1/agent_workflows/prompts/gwr_auditor_system_prompt.md

Key hard rules encoded in the system prompt: - Authority lock before any calculations - Fatal constraints before storage math - No assumption of missing data (NOT DEMONSTRATED classification) - K_design = K_field / 2.0 (FOS = 2.0) - Void ratio ceiling = 0.40 - 2026 SHWT reference = mound apex - 2026 NJGRS cover = Wooded/Good