Tables: Stormwater Management Quantity and Quality Standards and Computations

Back to source | Source PDF | Structured table records

Table fragments retain their source context. Refer to the original page for layout, figures, merged headings and notes.

1. Table 1

BMP 2026, Ch 5, p. 3

Recurrence Intervals and Probabilities of Occurrences
Recurrence Interval, in years Probability of Occurrence in any Given Year Percent Chance of Occurrence in any Given Year
100 1 in 100 1
50 1 in 50 2
25 1 in 25 4
10 1 in 10 10
5 1 in 5 20
2 1 in 2 50
Source context and notes Source revision: January 2026. - For example, the recurrence interval of a rainfall event that has a 50% chance of occurrence in a given year is expressed as the 2-year (= 100 ÷ 50) recurrence interval, which is also known as the 2-year storm. - For a storm event with a 1% chance of occurrence, it has a 100-year (= 100 ÷ 1) recurrence interval and is referred to as the 100-year storm. Referring to a precipitation event as the "X-year storm" does not mean that this storm can only happen once every X years. Nor does it mean that a larger storm event cannot also occur that year. The table below lists the probability of a particular occurrence and its corresponding chance of occurring, expressed as a percentage, in a single year. | Recurrence Intervals and Probabilities of Occurrences | | | | --- | --- | --- | | Recurrence Interval, in years | Probability of Occurrence in any Given Year | Percent Chance of Occurrence in any Given Year | | 100 | 1 in 100 | 1 | | 50 | 1 in 50 | 2 | | 25 | 1 in 25 | 4 | | 10 | 1 in 10 | 10 | | 5 | 1 in 5 | 20 | | 2 | 1 in 2 | 50 | Another aspect of the frequency analysis is the duration of rainfall events. The frequency analysis may use the rainfall depths observed in events having various durations of precipitation, such as 1 hour, 6 hours, or even 3 days, although a 24-hour duration is typically used. There are organizations that collect and publish hydrological data, such as National Oceanic and Atmospheric Administration's (NOAA) National Weather Service (NWS), which publishes and updates hydrological data and frequency analysis of rainfall depth and intensity constantly, under normal operating conditions. The National Engineering Handbook (NEH) produced by the NRCS uses NWS data due to its availability and lengths of record. Therefore, in this chapter, NOAA data is referenced in the calculations involving the rainfall depths and intensities for the 2-, 10- and 100-year storm events. A more detailed discussion of using NOAA data is found beginning on Page 13. # Regulatory Requirements of the Stormwater Management Rules

2. Table 5-1: NRCS Methodology Index of Information Required

BMP 2026, Ch 5, p. 11

Topic No. Information Required to use the NRCS Methodology Page No.
1 Hydrologic Soil Group of the drainage area soil 12
2 Sub-drainage areas 12
3 Land cover 12
4 Rainfall depth for the stormwater runoff quantity control design storms 13
5 Rainfall distribution for the stormwater runoff quantity control design storms 20
6 Rainfall depth for the stormwater runoff water quality design storm 21
7 Rainfall distribution for the stormwater runoff water quality design storm 21
8 Time of travel and time of concentration 24
8 Maximum sheet flow roughness coefficient 24
8 Sheet flow length 25
8 Shallow concentrated flow 26
8 Open channel flow 27
8 T_{c} routes 28
9 Runoff Hydrographs 28
10 Directly Connected Impervious Cover 31
11 Unconnected Impervious Cover 32
12 Reduced Curve Numbers 33
13 Calculating the Peak Flow Rate of Runoff for the WQDS 33
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Table 5-1: NRCS Methodology Index of Information Required | Topic No. | Information Required to use the NRCS Methodology | Page No. | | --- | --- | --- | | 1 | Hydrologic Soil Group of the drainage area soil | 12 | | 2 | Sub-drainage areas | 12 | | 3 | Land cover | 12 | | 4 | Rainfall depth for the stormwater runoff quantity control design storms | 13 | | 5 | Rainfall distribution for the stormwater runoff quantity control design storms | 20 | | 6 | Rainfall depth for the stormwater runoff water quality design storm | 21 | | 7 | Rainfall distribution for the stormwater runoff water quality design storm | 21 | | 8 | Time of travel and time of concentration | 24 | | 8 | Maximum sheet flow roughness coefficient | 24 | | 8 | Sheet flow length | 25 | | 8 | Shallow concentrated flow | 26 | | 8 | Open channel flow | 27 | | 8 | T_{c} routes | 28 | | 9 | Runoff Hydrographs | 28 | | 10 | Directly Connected Impervious Cover | 31 | | 11 | Unconnected Impervious Cover | 32 | | 12 | Reduced Curve Numbers | 33 | | 13 | Calculating the Peak Flow Rate of Runoff for the WQDS | 33 |

3. Table 5-2: County-Specific, New Jersey 24-Hour Rainfall Frequency Data

BMP 2026, Ch 5, p. 16

NEW JERSEY 24 HOUR RAINFALL FREQUENCY DATA
Rainfall amounts in Inches
County 1 year 2 year 5 year 10 year 25 year 50 year 100 year
Atlantic 2.72 3.31 4.30 5.16 6.46 7.61 8.90
Bergen 2.75 3.34 4.27 5.07 6.28 7.32 8.47
Burlington 2.77 3.36 4.34 5.18 6.45 7.56 8.81
Camden 2.73 3.31 4.25 5.06 6.28 7.34 8.52
Cape May 2.67 3.25 4.22 5.07 6.34 7.47 8.73
Cumberland 2.69 3.27 4.25 5.09 6.37 7.49 8.76
Essex 2.85 3.44 4.40 5.22 6.44 7.49 8.66
Gloucester 2.71 3.29 4.24 5.05 6.29 7.36 8.55
Hudson 2.73 3.31 4.23 5.02 6.19 7.20 8.31
Hunterdon 2.80 3.38 4.26 5.00 6.09 7.02 8.03
Mercer 2.74 3.31 4.23 5.01 6.19 7.20 8.33
Middlesex 2.76 3.35 4.30 5.12 6.36 7.43 8.63
Monmouth 2.79 3.38 4.38 5.23 6.53 7.66 8.94
Morris 2.94 3.54 4.47 5.24 6.37 7.32 8.35
Ocean 2.81 3.42 4.45 5.33 6.68 7.87 9.20
Passaic 2.87 3.47 4.42 5.23 6.43 7.47 8.62
Salem 2.69 3.26 4.20 5.00 6.22 7.28 8.45
Somerset 2.76 3.34 4.25 5.01 6.15 7.13 8.21
Sussex 2.68 3.22 4.02 4.70 5.72 6.60 7.58
Union 2.80 3.39 4.35 5.17 6.42 7.49 8.69
Warren 2.78 3.34 4.18 4.89 5.93 6.83 7.82
Notes: The average point rainfall amounts listed above were developed from data contained in NOAA Atlas 14 Volume 2.
Point rainfall estimates for specific locations may be obtained from the Precipitation Frequency Data Server located at http://www.nws.noa.gov/ohd/hdsc/.
For most hydrologic design procedures, the rainfall amounts listed above may be rounded to the nearest tenth of an inch.
Source context and notes Source revision: January 2026. ii. N.J.A.C. 7:8-5.7(c) and N.J.A.C. 7:8-5.7(d) both allow an alternative to calculating the current and projected rainfall precipitation depths by using separate rainfall totals for each county. The 24-hour county rainfall amount provided by NRCS is duplicated here and can be found online at: https://www.nrcs.usda.gov/sites/default/files/2022-09/NJ%2024%20Hour%20Rainfall%20Data.pdf. Table 5-2: County-Specific, New Jersey 24-Hour Rainfall Frequency Data | NEW JERSEY 24 HOUR RAINFALL FREQUENCY DATA | | | | | | | | | --- | --- | --- | --- | --- | --- | --- | --- | | Rainfall amounts in Inches | | | | | | | | | County | 1 year | 2 year | 5 year | 10 year | 25 year | 50 year | 100 year | | Atlantic | 2.72 | 3.31 | 4.30 | 5.16 | 6.46 | 7.61 | 8.90 | | Bergen | 2.75 | 3.34 | 4.27 | 5.07 | 6.28 | 7.32 | 8.47 | | Burlington | 2.77 | 3.36 | 4.34 | 5.18 | 6.45 | 7.56 | 8.81 | | Camden | 2.73 | 3.31 | 4.25 | 5.06 | 6.28 | 7.34 | 8.52 | | Cape May | 2.67 | 3.25 | 4.22 | 5.07 | 6.34 | 7.47 | 8.73 | | Cumberland | 2.69 | 3.27 | 4.25 | 5.09 | 6.37 | 7.49 | 8.76 | | Essex | 2.85 | 3.44 | 4.40 | 5.22 | 6.44 | 7.49 | 8.66 | | Gloucester | 2.71 | 3.29 | 4.24 | 5.05 | 6.29 | 7.36 | 8.55 | | Hudson | 2.73 | 3.31 | 4.23 | 5.02 | 6.19 | 7.20 | 8.31 | | Hunterdon | 2.80 | 3.38 | 4.26 | 5.00 | 6.09 | 7.02 | 8.03 | | Mercer | 2.74 | 3.31 | 4.23 | 5.01 | 6.19 | 7.20 | 8.33 | | Middlesex | 2.76 | 3.35 | 4.30 | 5.12 | 6.36 | 7.43 | 8.63 | | Monmouth | 2.79 | 3.38 | 4.38 | 5.23 | 6.53 | 7.66 | 8.94 | | Morris | 2.94 | 3.54 | 4.47 | 5.24 | 6.37 | 7.32 | 8.35 | | Ocean | 2.81 | 3.42 | 4.45 | 5.33 | 6.68 | 7.87 | 9.20 | | Passaic | 2.87 | 3.47 | 4.42 | 5.23 | 6.43 | 7.47 | 8.62 | | Salem | 2.69 | 3.26 | 4.20 | 5.00 | 6.22 | 7.28 | 8.45 | | Somerset | 2.76 | 3.34 | 4.25 | 5.01 | 6.15 | 7.13 | 8.21 | | Sussex | 2.68 | 3.22 | 4.02 | 4.70 | 5.72 | 6.60 | 7.58 | | Union | 2.80 | 3.39 | 4.35 | 5.17 | 6.42 | 7.49 | 8.69 | | Warren | 2.78 | 3.34 | 4.18 | 4.89 | 5.93 | 6.83 | 7.82 | | Notes: The average point rainfall amounts listed above were developed from data contained in NOAA Atlas 14 Volume 2.
Point rainfall estimates for specific locations may be obtained from the Precipitation Frequency Data Server located at http://www.nws.noa.gov/ohd/hdsc/.
For most hydrologic design procedures, the rainfall amounts listed above may be rounded to the nearest tenth of an inch. | | | | | | | |

4. Table 4

BMP 2026, Ch 5, p. 17

County Current Precipitation Adjustment Factors
2-year Design Storm 10-year Design Storm 100-year Design Storm
Atlantic 1.01 1.02 1.03
Bergen 1.01 1.03 1.06
Burlington 0.99 1.01 1.04
Camden 1.03 1.04 1.05
Cape May 1.03 1.03 1.04
Cumberland 1.03 1.03 1.01
Essex 1.01 1.03 1.06
Gloucester 1.05 1.06 1.06
Hudson 1.03 1.05 1.09
Hunterdon 1.02 1.05 1.13
Mercer 1.01 1.02 1.04
Middlesex 1.00 1.01 1.03
Monmouth 1.00 1.01 1.02
Morris 1.01 1.03 1.06
Ocean 1.00 1.01 1.03
Passaic 1.00 1.02 1.05
Salem 1.02 1.03 1.03
Somerset 1.00 1.03 1.09
Sussex 1.03 1.04 1.07
Union 1.01 1.03 1.06
Warren 1.02 1.07 1.15
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. b. N.J.A.C.7:8-5.7(c) requires the precipitation depths of the current 2-, 10- and 100-year storm events be determined by multiplying the NOAA rainfall data with the current precipitation adjustment factors in Table 5-5 at N.J.A.C.7:8-5.7(c)2. N.J.A.C.7:8-5.7(d) requires the precipitation depths of the projected 2-, 10- and 100-year storm events be determined by multiplying the NOAA rainfall data with the future precipitation change factors in Table 5-6 at N.J.A.C.7:8-5.7(d). Table 5-5 and Table 5-6 from the Rules are reproduced below. Current Precipitation Adjustment Factors at N.J.A.C. 7:8-5.7(c) as Table 5-5 | County | Current Precipitation Adjustment Factors | | | | --- | --- | --- | --- | | | 2-year Design Storm | 10-year Design Storm | 100-year Design Storm | | Atlantic | 1.01 | 1.02 | 1.03 | | Bergen | 1.01 | 1.03 | 1.06 | | Burlington | 0.99 | 1.01 | 1.04 | | Camden | 1.03 | 1.04 | 1.05 | | Cape May | 1.03 | 1.03 | 1.04 | | Cumberland | 1.03 | 1.03 | 1.01 | | Essex | 1.01 | 1.03 | 1.06 | | Gloucester | 1.05 | 1.06 | 1.06 | | Hudson | 1.03 | 1.05 | 1.09 | | Hunterdon | 1.02 | 1.05 | 1.13 | | Mercer | 1.01 | 1.02 | 1.04 | | Middlesex | 1.00 | 1.01 | 1.03 | | Monmouth | 1.00 | 1.01 | 1.02 | | Morris | 1.01 | 1.03 | 1.06 | | Ocean | 1.00 | 1.01 | 1.03 | | Passaic | 1.00 | 1.02 | 1.05 | | Salem | 1.02 | 1.03 | 1.03 | | Somerset | 1.00 | 1.03 | 1.09 | | Sussex | 1.03 | 1.04 | 1.07 | | Union | 1.01 | 1.03 | 1.06 | | Warren | 1.02 | 1.07 | 1.15 |

5. Table 5

BMP 2026, Ch 5, p. 18

County Future Precipitation Change Factors
2-year Design Storm 10-year Design Storm 100-year Design Storm
Atlantic 1.22 1.24 1.39
Bergen 1.20 1.23 1.37
Burlington 1.17 1.18 1.32
Camden 1.18 1.22 1.39
Cape May 1.21 1.24 1.32
Cumberland 1.20 1.21 1.39
Essex 1.19 1.22 1.33
Gloucester 1.19 1.23 1.41
Hudson 1.19 1.19 1.23
Hunterdon 1.19 1.23 1.42
Mercer 1.16 1.17 1.36
Middlesex 1.19 1.21 1.33
Monmouth 1.19 1.19 1.26
Morris 1.23 1.28 1.46
Ocean 1.18 1.19 1.24
Passaic 1.21 1.27 1.50
Salem 1.20 1.23 1.32
Somerset 1.19 1.24 1.48
Sussex 1.24 1.29 1.50
Union 1.20 1.23 1.35
Warren 1.20 1.25 1.37
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Future Precipitation Change Factors at N.J.A.C. 7:8-5.7(d) as Table 5-6 | County | Future Precipitation Change Factors | | | | --- | --- | --- | --- | | | 2-year Design Storm | 10-year Design Storm | 100-year Design Storm | | Atlantic | 1.22 | 1.24 | 1.39 | | Bergen | 1.20 | 1.23 | 1.37 | | Burlington | 1.17 | 1.18 | 1.32 | | Camden | 1.18 | 1.22 | 1.39 | | Cape May | 1.21 | 1.24 | 1.32 | | Cumberland | 1.20 | 1.21 | 1.39 | | Essex | 1.19 | 1.22 | 1.33 | | Gloucester | 1.19 | 1.23 | 1.41 | | Hudson | 1.19 | 1.19 | 1.23 | | Hunterdon | 1.19 | 1.23 | 1.42 | | Mercer | 1.16 | 1.17 | 1.36 | | Middlesex | 1.19 | 1.21 | 1.33 | | Monmouth | 1.19 | 1.19 | 1.26 | | Morris | 1.23 | 1.28 | 1.46 | | Ocean | 1.18 | 1.19 | 1.24 | | Passaic | 1.21 | 1.27 | 1.50 | | Salem | 1.20 | 1.23 | 1.32 | | Somerset | 1.19 | 1.24 | 1.48 | | Sussex | 1.24 | 1.29 | 1.50 | | Union | 1.20 | 1.23 | 1.35 | | Warren | 1.20 | 1.25 | 1.37 |

6. Table 6

BMP 2026, Ch 5, p. 19

Frequency of Storms NOAA NWS PFDS Rainfall Depth (inches) Current Precipitation Adjustment Factor Current Rainfall Depth (inches)
2-year 3.33 1.01 3.36
10-year 4.99 1.02 5.09
100-year 8.15 1.04 8.48
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Example B-1: Apply the current precipitation adjustment factors for the site depicted in Example A-1. The table below includes the rainfall depths from Example A-1 and the Mercer County current precipitation adjustment factors from Table 5-5 in the Stormwater Management rules for the site located in Trenton, NJ. To obtain the current precipitation depth for the 2-year design storm, multiply the precipitation depth for the 2-year design storm by the 2-year current precipitation adjustment factor. Repeat the process for the 10- and 100-year design storms using the respective adjustment factor. The results are depicted in the column farthest to the right in the table below. | Frequency of Storms | NOAA NWS PFDS Rainfall Depth (inches) | Current Precipitation Adjustment Factor | Current Rainfall Depth (inches) | | --- | --- | --- | --- | | 2-year | 3.33 | 1.01 | 3.36 | | 10-year | 4.99 | 1.02 | 5.09 | | 100-year | 8.15 | 1.04 | 8.48 | Example B-2: Determine the current precipitation adjustment factors for a site with one-third of the area located in Middlesex County and the remainder in Mercer County. In the event a project spans the boundary line(s) between counties, N.J.A.C. 7:8-5.7(c)2 instructs the user as follows: "Where the major development lies in more than one county, the precipitation values shall be adjusted according to the percentage of the drainage area in each county." Step 1: Obtain the current precipitation for each of the counties.

7. Table 7

BMP 2026, Ch 5, p. 19

County Current Precipitation
2-year Design Storm 10-year Design Storm 100-year Design Storm
Middlesex 3.35 * 1.00 = 3.35 5.12 * 1.01 = 5.17 8.63 * 1.03 = 8.89
Mercer 3.31 * 1.01 = 3.34 5.01 * 1.02 = 5.11 8.33 * 1.04 = 8.66
Source context and notes | 100-year | 8.15 | 1.04 | 8.48 | Example B-2: Determine the current precipitation adjustment factors for a site with one-third of the area located in Middlesex County and the remainder in Mercer County. In the event a project spans the boundary line(s) between counties, N.J.A.C. 7:8-5.7(c)2 instructs the user as follows: "Where the major development lies in more than one county, the precipitation values shall be adjusted according to the percentage of the drainage area in each county." Step 1: Obtain the current precipitation for each of the counties. | County | Current Precipitation | | | | --- | --- | --- | --- | | | 2-year Design Storm | 10-year Design Storm | 100-year Design Storm | | Middlesex | 3.35 * 1.00 = 3.35 | 5.12 * 1.01 = 5.17 | 8.63 * 1.03 = 8.89 | | Mercer | 3.31 * 1.01 = 3.34 | 5.01 * 1.02 = 5.11 | 8.33 * 1.04 = 8.66 | The method is the same as that shown above in Example A-1, but is performed for each of counties using the respective current precipitation adjustment factor. Step 2: Multiply the percentage of the project area within each county with the current precipitation for the respective county, and sum the results for each of the design storms, pursuant to N.J.A.C. 7:8-5.7(c)2. The results are shown in the following table.

8. Table 8

BMP 2026, Ch 5, p. 20

County, Weight Averaged Current Precipitation
2-year Design Storm 10-year Design Storm 100-year Design Storm
Middlesex 0.333 * 3.35 = 1.12 0.333 * 5.17 = 1.72 0.333 * 8.89 = 2.96
Mercer + 0.667 * 3.34 = 2.23 + 0.667 * 5.11 = 3.41 + 0.667 * 8.66 = 5.78
Total Site Precipitation 3.35 5.13 8.74
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | County, Weight Averaged | Current Precipitation | | | | --- | --- | --- | --- | | | 2-year Design Storm | 10-year Design Storm | 100-year Design Storm | | Middlesex | 0.333 * 3.35 = 1.12 | 0.333 * 5.17 = 1.72 | 0.333 * 8.89 = 2.96 | | Mercer | + 0.667 * 3.34 = 2.23 | + 0.667 * 5.11 = 3.41 | + 0.667 * 8.66 = 5.78 | | Total Site Precipitation | 3.35 | 5.13 | 8.74 | 5. Rainfall distribution for the stormwater runoff quantity control design storms: In addition to the rainfall depth, knowing how rain falls during a storm event is important in calculating the peak flow rate of the stormwater runoff generated. Keep in mind that, generally, a precipitation event typically begins with a lighter intensity of rain falling, followed by a period during which rain falls at a higher intensity before gently tapering off. To achieve the goal of estimating rainfall events for design and planning purposes, between 1961 and 1977, NRCS developed synthetic rainfall distributions from historical records from the different regions of the country. These rainfall distributions were based upon the assumption that the rain distribution is bell-shaped, meaning it has less rainfall in the beginning and at the end of the rain event. The NRCS rainfall distributions were grouped into four types according to the applicable regions or geographic situations. Types I and IA represented the Pacific maritime climate with wet winters and dry summers. Type III represented the Gulf of Mexico and Atlantic coastal areas, including New Jersey, where tropical storms produced large 24-hour rainfall events. Type II represented the rest of the country. These NRCS rainfall distributions had durations of 24-, 18-, 12- or 6-hours. On September 10, 2012, NCRS issued a note, NEW JERSEY BULLETIN NO. NJ210-12-1, stating that: Based on updated rainfall data from NOAA, NRCS has developed new storm distributions for use with EFH-2 and WinTR-55. New Jersey has two new rainfall distribution regions: Region C covering the counties of Sussex, Warren, Hunterdon, Somerset, Mercer, Burlington, Camden, Gloucester, Atlantic, Salem, Cumberland, and Cape May; and Region D covering Bergen, Hudson, Essex, Passaic, Morris, Union, Middlesex, Monmouth and Ocean. The new rainfall distributions replace use of the TYPE III distribution in New Jersey. The 24-hour rainfall-frequency data has been updated as well with only minor variations for some of the counties.

9. Table 5-3: NJDEP 1.25-Inch/2-Hour Stormwater Runoff Water Quality Design Storm Rainfall Distribution

BMP 2026, Ch 5, p. 23

Time (Minutes) Cumulative Rainfall (Inches) Time (Minutes) Cumulative Rainfall (Inches) Time (Minutes) Cumulative Rainfall (Inches)
1 0.00166 41 0.1728 81 1.0906
2 0.00332 42 0.1796 82 1.0972
3 0.00498 43 0.1864 83 1.1038
4 0.00664 44 0.1932 84 1.1104
5 0.00830 45 0.2000 85 1.1170
6 0.00996 46 0.2117 86 1.1236
7 0.01162 47 0.2233 87 1.1302
8 0.01328 48 0.2350 88 1.1368
9 0.01494 49 0.2466 89 1.1434
10 0.01660 50 0.2583 90 1.1500
11 0.01828 51 0.2783 91 1.1550
12 0.01996 52 0.2983 92 1.1600
13 0.02164 53 0.3183 93 1.1650
14 0.02332 54 0.3383 94 1.1700
15 0.02500 55 0.3583 95 1.1750
16 0.03000 56 0.4116 96 1.1800
17 0.03500 57 0.4650 97 1.1850
18 0.04000 58 0.5183 98 1.1900
19 0.04500 59 0.5717 99 1.1950
20 0.05000 60 0.6250 100 1.2000
21 0.05500 61 0.6783 101 1.2050
22 0.06000 62 0.7317 102 1.2100
23 0.06500 63 0.7850 103 1.2150
24 0.07000 64 0.8384 104 1.2200
25 0.07500 65 0.8917 105 1.2250
26 0.08000 66 0.9117 106 1.2267
27 0.08500 67 0.9317 107 1.2284
28 0.09000 68 0.9517 108 1.2300
29 0.09500 69 0.9717 109 1.2317
30 0.10000 70 0.9917 110 1.2334
31 0.10660 71 1.0034 111 1.2351
32 0.11320 72 1.0150 112 1.2367
33 0.11980 73 1.0267 113 1.2384
34 0.12640 74 1.0383 114 1.2400
35 0.13300 75 1.0500 115 1.2417
36 0.13960 76 1.0568 116 1.2434
37 0.14620 77 1.0636 117 1.2450
38 0.15280 78 1.0704 118 1.2467
39 0.15940 79 1.0772 119 1.2483
40 0.16600 80 1.0840 120 1.2500
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Table 5-3: NJDEP 1.25-Inch/2-Hour Stormwater Runoff Water Quality Design Storm Rainfall Distribution | Time (Minutes) | Cumulative Rainfall (Inches) | Time (Minutes) | Cumulative Rainfall (Inches) | Time (Minutes) | Cumulative Rainfall (Inches) | | --- | --- | --- | --- | --- | --- | | 1 | 0.00166 | 41 | 0.1728 | 81 | 1.0906 | | 2 | 0.00332 | 42 | 0.1796 | 82 | 1.0972 | | 3 | 0.00498 | 43 | 0.1864 | 83 | 1.1038 | | 4 | 0.00664 | 44 | 0.1932 | 84 | 1.1104 | | 5 | 0.00830 | 45 | 0.2000 | 85 | 1.1170 | | 6 | 0.00996 | 46 | 0.2117 | 86 | 1.1236 | | 7 | 0.01162 | 47 | 0.2233 | 87 | 1.1302 | | 8 | 0.01328 | 48 | 0.2350 | 88 | 1.1368 | | 9 | 0.01494 | 49 | 0.2466 | 89 | 1.1434 | | 10 | 0.01660 | 50 | 0.2583 | 90 | 1.1500 | | 11 | 0.01828 | 51 | 0.2783 | 91 | 1.1550 | | 12 | 0.01996 | 52 | 0.2983 | 92 | 1.1600 | | 13 | 0.02164 | 53 | 0.3183 | 93 | 1.1650 | | 14 | 0.02332 | 54 | 0.3383 | 94 | 1.1700 | | 15 | 0.02500 | 55 | 0.3583 | 95 | 1.1750 | | 16 | 0.03000 | 56 | 0.4116 | 96 | 1.1800 | | 17 | 0.03500 | 57 | 0.4650 | 97 | 1.1850 | | 18 | 0.04000 | 58 | 0.5183 | 98 | 1.1900 | | 19 | 0.04500 | 59 | 0.5717 | 99 | 1.1950 | | 20 | 0.05000 | 60 | 0.6250 | 100 | 1.2000 | | 21 | 0.05500 | 61 | 0.6783 | 101 | 1.2050 | | 22 | 0.06000 | 62 | 0.7317 | 102 | 1.2100 | | 23 | 0.06500 | 63 | 0.7850 | 103 | 1.2150 | | 24 | 0.07000 | 64 | 0.8384 | 104 | 1.2200 | | 25 | 0.07500 | 65 | 0.8917 | 105 | 1.2250 | | 26 | 0.08000 | 66 | 0.9117 | 106 | 1.2267 | | 27 | 0.08500 | 67 | 0.9317 | 107 | 1.2284 | | 28 | 0.09000 | 68 | 0.9517 | 108 | 1.2300 | | 29 | 0.09500 | 69 | 0.9717 | 109 | 1.2317 | | 30 | 0.10000 | 70 | 0.9917 | 110 | 1.2334 | | 31 | 0.10660 | 71 | 1.0034 | 111 | 1.2351 | | 32 | 0.11320 | 72 | 1.0150 | 112 | 1.2367 | | 33 | 0.11980 | 73 | 1.0267 | 113 | 1.2384 | | 34 | 0.12640 | 74 | 1.0383 | 114 | 1.2400 | | 35 | 0.13300 | 75 | 1.0500 | 115 | 1.2417 | | 36 | 0.13960 | 76 | 1.0568 | 116 | 1.2434 | | 37 | 0.14620 | 77 | 1.0636 | 117 | 1.2450 | | 38 | 0.15280 | 78 | 1.0704 | 118 | 1.2467 | | 39 | 0.15940 | 79 | 1.0772 | 119 | 1.2483 | | 40 | 0.16600 | 80 | 1.0840 | 120 | 1.2500 |

10. Table 15-1 Manning's roughness coefficients for sheet flow (flow depth generally ≤ 0.1 ft)

BMP 2026, Ch 5, p. 25

Table 15-1 Manning's roughness coefficients for sheet flow (flow depth generally ≤ 0.1 ft)
Surface description n1/
Smooth surface (concrete, asphalt, gravel, or bare soil) 0.011
Fallow (no residue) 0.05
Cultivated soils:
Residue cover ≤ 20% 0.06
Residue cover > 20% 0.17
Grass:
Short-grass prairie 0.15
Dense grasses2/ 0.24
Bermudagrass 0.41
Range (natural) 0.13
Woods:3/
Light underbrush 0.40
Dense underbrush 0.80
1 The Manning's n values are a composite of information compiled by Engman (1986).
2 Includes species such as weeping lovegrass, bluegrass, buffalo grass, blue grama grass, and native grass mixtures.
3 When selecting n, consider cover to a height of about 0.1 ft. This is the only part of the plant cover that will obstruct sheet flow.
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Figure 5-12: Manning's Roughness Coefficients for Sheet Flow | Table 15-1 Manning's roughness coefficients for sheet flow (flow depth generally ≤ 0.1 ft) | | | --- | --- | | Surface description | n1/ | | Smooth surface (concrete, asphalt, gravel, or bare soil) | 0.011 | | Fallow (no residue) | 0.05 | | Cultivated soils: | | | Residue cover ≤ 20% | 0.06 | | Residue cover > 20% | 0.17 | | Grass: | | | Short-grass prairie | 0.15 | | Dense grasses2/ | 0.24 | | Bermudagrass | 0.41 | | Range (natural) | 0.13 | | Woods:3/ | | | Light underbrush | 0.40 | | Dense underbrush | 0.80 | | 1 The Manning's n values are a composite of information compiled by Engman (1986). | | | 2 Includes species such as weeping lovegrass, bluegrass, buffalo grass, blue grama grass, and native grass mixtures. | | | 3 When selecting n, consider cover to a height of about 0.1 ft. This is the only part of the plant cover that will obstruct sheet flow. | | - Sheet Flow Length: ☐ For the pre-construction condition, the user assumes a sheet flow length of 100 ft. Only when there is something physically in contact with the flow of stormwater runoff to prevent sheet flow from occurring, such as a swale, curb or inlet, shall the value used be less than 100 ft. ☐ For the post-construction condition, the maximum sheet flow length should not exceed the McCuen-Spiess limitation or 100 ft, whichever is shorter. The McCuen-Spiess limitation is calculated as follows:

11. Table 15-3 Equations and assumptions developed from figure 15-4

BMP 2026, Ch 5, p. 26

Table 15-3 Equations and assumptions developed from figure 15-4
Flow type Depth (ft) Manning's n Velocity equation (ft/s)
Pavement and small upland gullies 0.2 0.025 V=20.328(s)1-1
Grassed waterways 0.4 0.050 V=16.135(s)1-1
Nearly bare and untilled (overland flow); and alluvial fans in western mountain regions 0.2 0.051 V=9.965(s)2-2
Cultivated straight row crops 0.2 0.058 V=8.762(s)2-2
Short-grass pasture 0.2 0.073 V=6.962(s)2-2
Minimum tillage cultivation, contour or strip-cropped, and woodlands 0.2 0.101 V=5.032(s)2-2
Forest with heavy ground litter and hay meadows 0.2 0.202 V=2.516(s)2-2
Source context and notes ☐ When calculating the travel time for current storm events, use the precipitation depth for the current 2-year storm event, which is calculated by multiplying either the NOAA NWS PFDS rainfall depth or the NRCS county rainfall data for the 2-year storm by the current precipitation adjustment factors. ☐ When calculating the travel time for projected storm events, use the precipitation depth of the projected 2-year storm event, which is calculated by multiplying either the NOAA NWS PFDS rainfall depth or the NRCS county rainfall data for the 2-year storm by the future precipitation change factors. - Calculating the travel time for a segment in which shallow concentrated flow occurs: Shallow concentrated flow occurs after sheet flow, and the depths range from 0.1 to 0.5 ft. The value for the flow velocity can be determined from the graphical source, reprinted as Figure 5-14 on the next page, is Figure 15-4 in NEH, Part 630, Chapter 15. This source was derived by solving Manning's equation for a wide variety of land covers; Figure 5-13 below is Table 15-3 in NEH, Part 630, Chapter 15, Equations and assumptions developed from figure 15-4. The velocities plotted in each are average values and are a function of watercourse slope and the cover condition of the channel. To use this figure, find the slope on the y-axis, noting it is a logarithmic in scale, and project a horizontal line over to the line which best fits the cover present for this segment of flow. Then draw a vertical line to the x-axis and read the velocity, taking note that the x-axis is also logarithmic in scale. Figure 5-13: Equations and assumptions from Figure 15-4 From NEH, Part 630, Chapter 15 | Table 15-3 Equations and assumptions developed from figure 15-4 | | | | | --- | --- | --- | --- | | Flow type | Depth (ft) | Manning's n | Velocity equation (ft/s) | | Pavement and small upland gullies | 0.2 | 0.025 | V=20.328(s)1-1 | | Grassed waterways | 0.4 | 0.050 | V=16.135(s)1-1 | | Nearly bare and untilled (overland flow); and alluvial fans in western mountain regions | 0.2 | 0.051 | V=9.965(s)2-2 | | Cultivated straight row crops | 0.2 | 0.058 | V=8.762(s)2-2 | | Short-grass pasture | 0.2 | 0.073 | V=6.962(s)2-2 | | Minimum tillage cultivation, contour or strip-cropped, and woodlands | 0.2 | 0.101 | V=5.032(s)2-2 | | Forest with heavy ground litter and hay meadows | 0.2 | 0.202 | V=2.516(s)2-2 |

12. Table 12

BMP 2026, Ch 5, p. 34

Example No. Scenario Description Page No.
5-1 Calculate of Time of Concentration 34
5-2 Use the NRCS CN Method for an Unconnected Impervious Surface to Calculate the Runoff Volume for a Site 37
5-3 Use the NJDEP Two-Step Method for an Unconnected Impervious Surface to Calculate the Runoff Volume for a Site 39
5-4 Demonstration of Why a Composite CN Generates an Incorrect Runoff Volume 40
5-5 A Comparison of Pre- and Post-condition Hydrographs for Compliance Under N.J.A.C. 7:8-5.6(b)1 When Impervious Cover is Reduced 42
5-6 A Re-development Project with Two Drainage Areas, Each Discharging to Separate Points, 48
5-7 The Same Re-development Project with Two Drainage Areas, having One Combined Discharge Point 69
5-8 A 2- Acre Development Project with GI BMPs Illustrating the Use of Current and Projected Storm Events in the Design Calculations to address the Water Quality, Runoff Quantity Control and Groundwater Recharge Requirements 72
5-9 Calculate the Volume and Peak Flow Rate for the Runoff Produced by the WQDS Falling on 0.25 Acres of Regulated Motor Vehicle Surface to be Treated by a Manufactured Treatment Device 84
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Example No. | Scenario Description | Page No. | | --- | --- | --- | | 5-1 | Calculate of Time of Concentration | 34 | | 5-2 | Use the NRCS CN Method for an Unconnected Impervious Surface to Calculate the Runoff Volume for a Site | 37 | | 5-3 | Use the NJDEP Two-Step Method for an Unconnected Impervious Surface to Calculate the Runoff Volume for a Site | 39 | | 5-4 | Demonstration of Why a Composite CN Generates an Incorrect Runoff Volume | 40 | | 5-5 | A Comparison of Pre- and Post-condition Hydrographs for Compliance Under N.J.A.C. 7:8-5.6(b)1 When Impervious Cover is Reduced | 42 | | 5-6 | A Re-development Project with Two Drainage Areas, Each Discharging to Separate Points, | 48 | | 5-7 | The Same Re-development Project with Two Drainage Areas, having One Combined Discharge Point | 69 | | 5-8 | A 2- Acre Development Project with GI BMPs Illustrating the Use of Current and Projected Storm Events in the Design Calculations to address the Water Quality, Runoff Quantity Control and Groundwater Recharge Requirements | 72 | | 5-9 | Calculate the Volume and Peak Flow Rate for the Runoff Produced by the WQDS Falling on 0.25 Acres of Regulated Motor Vehicle Surface to be Treated by a Manufactured Treatment Device | 84 | ## Example 5-1: Calculate Time of Concentration For a site located in Mercer County, stormwater runoff flows through a wooded drainage area along a flow path, measuring 1,000 ft in length, consisting of sheet flow over an area with a 0.5% slope and shallow concentrated flow over an area of 1% slope. Calculate the time of concentration using current rainfall data. **Step 1:** In this example, there are only 2 different segments of flow. Travel time under sheet flow is calculated as follows:

13. Table 13

BMP 2026, Ch 5, p. 43

Frequency of Storms NOAA NWS PFDS Precipitation Depth (inches) Current Precipitation Adjustment Factor Current Rainfall Depth (inches) Projected Precipitation Change Factor Projected Rainfall Depth (inches)
2-year 3.33 1.01 3.36 1.16 3.86
10-year 4.99 1.02 5.09 1.17 5.83
100-year 8.15 1.04 8.48 1.36 11.08
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Frequency of Storms | NOAA NWS PFDS Precipitation Depth (inches) | Current Precipitation Adjustment Factor | Current Rainfall Depth (inches) | Projected Precipitation Change Factor | Projected Rainfall Depth (inches) | | --- | --- | --- | --- | --- | --- | | 2-year | 3.33 | 1.01 | 3.36 | 1.16 | 3.86 | | 10-year | 4.99 | 1.02 | 5.09 | 1.17 | 5.83 | | 100-year | 8.15 | 1.04 | 8.48 | 1.36 | 11.08 | # Step 2: Calculate $\mathsf{T}_{\mathsf{c}}$ for the existing and proposed conditions. The site conditions and 2-year current rainfall depth are entered into hydrologic modelling software. For pavement, the value for Manning's roughness coefficient is 0.011, as shown in Table 15-1, in NEH, Part 630, Chapter 15, and reprinted on Page 25. The pre-construction drainage pattern consists of sheet flow for the first 100 ft, followed by shallow concentrated flow for 200 ft. $T_{c}$ is calculated to be 3.2 minutes. The post-construction drainage pattern remains the same as the existing condition, i.e., flowing from the north to the south. The slope, however, is increased from $1\%$ to $5\%$ . The time of concentration is calculated and shown in the table below. The sheet flow length calculated by McCuen-Spiess limitation criteria, where $S$ is the slope, in ft/ft, and $n$ is the Manning's roughness coefficient for sheet flow, is as follows:

14. Table 14

BMP 2026, Ch 5, p. 43

Surface Description Slope, S (ft/ft) Manning's Roughness Coefficient, n, For Sheet Flow McCuen-Spiess Limitation Sheet Flow Length (ft) Sheet Flow Length to be used in the Model (ft) Length of Shallow Concentrated Flow (ft) Calculated Tc(min) for Current Rainfall Depth
Building 0.05 0.011 2,036 441 236 1.3
Landscaped Area 0.05 0.150 149 1002 3453 10.3
Parking Area 0.05 0.011 2,036 100 136 0.9
Source context and notes The post-construction drainage pattern remains the same as the existing condition, i.e., flowing from the north to the south. The slope, however, is increased from $1\%$ to $5\%$ . The time of concentration is calculated and shown in the table below. The sheet flow length calculated by McCuen-Spiess limitation criteria, where $S$ is the slope, in ft/ft, and $n$ is the Manning's roughness coefficient for sheet flow, is as follows: $$ L = \frac {1 0 0 \sqrt {S}}{n} $$ and the calculated result exceeds 100 ft. Therefore, the sheet flow length must be limited to the maximum of 100 ft and the shallow concentrated flow length is 200 ft. However, the time of concentration for the building and parking area under the post-construction condition is shorter than the time of concentration for the pre-construction condition due to the increased slope. | Surface Description | Slope, S (ft/ft) | Manning's Roughness Coefficient, n, For Sheet Flow | McCuen-Spiess Limitation Sheet Flow Length (ft) | Sheet Flow Length to be used in the Model (ft) | Length of Shallow Concentrated Flow (ft) | Calculated Tc(min) for Current Rainfall Depth | | --- | --- | --- | --- | --- | --- | --- | | Building | 0.05 | 0.011 | 2,036 | 441 | 236 | 1.3 | | Landscaped Area | 0.05 | 0.150 | 149 | 1002 | 3453 | 10.3 | | Parking Area | 0.05 | 0.011 | 2,036 | 100 | 136 | 0.9 | Sheet Flow Length is limited by the building width of 44 ft 2 Sheet Flow Length = (100*sqrt(0.05))/0.150 = 149 ft; therefore, a maximum of 100 ft shall be used 3 Shallow Concentrated Flow Length = The half of the lot width subtracted by the sheet flow length + the lot length = 290/2 - 100 + 300 = 345 ft

15. Table 15

BMP 2026, Ch 5, p. 44

Projected 100-year Design Storm
Parameter Pre-Construction Condition Post-Construction Condition
Peak Flow Rate & Time of Peak = 25.71 cfs @ 12.10 hr 23.60 cfs @ 12.10 hr
Runoff Volume= 78,689.7 cf 75,250.3 cf
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Step 3: Calculate the peak flow rates for the projected 100-year storm for the pre- and post-construction conditions using the future precipitation change factor and compare the hydrographs. A summary of the results from the modelling software is shown in the table below: | Projected 100-year Design Storm | | | | --- | --- | --- | | Parameter | Pre-Construction Condition | Post-Construction Condition | | Peak Flow Rate & Time of Peak = | 25.71 cfs @ 12.10 hr | 23.60 cfs @ 12.10 hr | | Runoff Volume= | 78,689.7 cf | 75,250.3 cf | Pre- and post-condition hydrographs for the projected 100-year storm, after applying the future precipitation change factor to the NOAA NWS PFDS rainfall data, are depicted below. The hydrographs were created by exporting the hydrograph tables as CSV data and then using a spreadsheet program to graph the information. [Figure: img-24.jpeg (original PDF, p. 44)](SOURCE.pdf#page=44) At first glance, one might assume the difference is negligible. However, the Rules do not permit any exceedance. If one were to zoom in on the previous hydrograph, e.g., starting at 11.92 hours, one would see the post-construction hydrograph has a higher flow rate than the pre-construction hydrograph in certain time periods. Some of these exceedances are highlighted in yellow in the following graphic.

16. Table 16

BMP 2026, Ch 5, p. 45

Time (hr) Pre-construction (cfs) Post-construction (cfs) Difference in Flow Rate, Post - Pre, (cfs)
11.91 9.04 9.86 0.82
11.92 9.44 12.52 3.08
11.93 10.42 13.39 2.97
11.94 11.77 13.63 1.86
11.95 13.07 13.73 0.66
11.96 14.03 13.8 -0.23
11.97 14.63 13.87 -0.76
11.98 15 13.95 -1.05
11.99 15.22 14.03 -1.19
12 15.37 14.16 -1.21
12.01 15.53 16.59 1.06
12.02 16.16 20.87 4.71
12.03 17.74 22.30 4.56
12.04 19.96 22.71 2.75
12.05 22.05 22.90 0.85
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. [Figure: img-25.jpeg (original PDF, p. 45)](SOURCE.pdf#page=45) A portion of the hydrograph data is also listed in the table below, for which the exceedances are highlighted in yellow. Take note this is just one example of two clusters of exceedances for this storm. | Time (hr) | Pre-construction (cfs) | Post-construction (cfs) | Difference in Flow Rate, Post - Pre, (cfs) | | --- | --- | --- | --- | | 11.91 | 9.04 | 9.86 | 0.82 | | 11.92 | 9.44 | 12.52 | 3.08 | | 11.93 | 10.42 | 13.39 | 2.97 | | 11.94 | 11.77 | 13.63 | 1.86 | | 11.95 | 13.07 | 13.73 | 0.66 | | 11.96 | 14.03 | 13.8 | -0.23 | | 11.97 | 14.63 | 13.87 | -0.76 | | 11.98 | 15 | 13.95 | -1.05 | | 11.99 | 15.22 | 14.03 | -1.19 | | 12 | 15.37 | 14.16 | -1.21 | | 12.01 | 15.53 | 16.59 | 1.06 | | 12.02 | 16.16 | 20.87 | 4.71 | | 12.03 | 17.74 | 22.30 | 4.56 | | 12.04 | 19.96 | 22.71 | 2.75 | | 12.05 | 22.05 | 22.90 | 0.85 | Although the reduction of impervious surface reduces the total volume of runoff and peak flow rate produced by the proposed construction, the design is not in compliance with N.J.A.C. 7:8-5.6(b)1, which requires that the post-construction runoff hydrographs do not exceed, at any point in time, the pre-construction runoff hydrographs for the same storm events, if the design engineer chooses to demonstrate the quantity control using this option. Since the hydrographs for the projected 100-year storm have already shown noncompliance, this example does not continue further to calculate

17. Table 17

BMP 2026, Ch 5, p. 46

Projected 100-year Design Storm
Pre-Construction Peak Flow Rate Allowable Post-Construction (80% Reduction) Peak Flow Rate Post-Construction Peak Flow Rate
Peak Flow Rate = 25.71 cfs 20.57 cfs 23.60 cfs
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. hydrographs for the projected 2- and 10-year storms. Additionally, a similar comparison for the 2-, 10- and 100-year design storms using rainfall data with the current precipitation adjustment factors applied would be required to demonstrate compliance for the current design storms. On the other hand, if the design engineer chooses to demonstrate compliance with the quantity control requirements under N.J.A.C. 7:8-5.6(b)3, e.g., that the post-construction peak runoff rates for the projected 2-, 10- and 100-year storm events are 50, 75 and 80 percent, respectively, of the pre-construction peak runoff rates, the calculation of the peak flow rate for the projected 100-year storm will be as follows: | | Projected 100-year Design Storm | | | | --- | --- | --- | --- | | | Pre-Construction Peak Flow Rate | Allowable Post-Construction (80% Reduction) Peak Flow Rate | Post-Construction Peak Flow Rate | | Peak Flow Rate = | 25.71 cfs | 20.57 cfs | 23.60 cfs | The projected 100-year post-construction peak flow rate, 23.60 cfs, exceeds the allowable flow rate, 20.57 cfs. Therefore, the project is still not in compliance with the stormwater runoff quantity control requirement under the option found in N.J.A.C. 7:8-5.6(b)3. A stormwater runoff quantity control or green infrastructure BMP will be required to reduce the projected 100-year post-construction peak flow to 80%, or lower, of the pre-construction peak flow rate. # Step 4: Calculate the peak flow rates for other design storms for the pre- and post-construction conditions and compare the hydrographs In Step 3, the comparison of hydrographs for the pre- and post-construction projected 100-year design year storms has shown that a reduction of the impervious surface or runoff volume in a redevelopment project may not comply with N.J.A.C. 7:8-5.6(b). The rules require the demonstration of compliance with the requirements in N.J.A.C. 7:8-5.6(b) for the current and projected 2-, 10- and 100-year storms. Using the same technique in Step 3, a hydrograph comparison of the pre- and post- current 2-year storms, for example, is shown in the table below. To correctly calculate the time of concentration, first $P_{2}$ was calculated by multiplying the NOAA NWQ PFDS rainfall depth for the 2-year storm (3.33 in) with the current precipitation adjustment factor (1.01) and is equal to 3.36 in. Next, the modeling software is used to produce the hydrographs, with the peak flow rates and time intervals exported as data for input into a spreadsheet to create a chart. Here is the summary information.

18. Table 18

BMP 2026, Ch 5, p. 46

Current 2-year Design Storm
Parameter Pre-Construction Condition Post-Construction Condition
Peak Flow Rate & Time of Peak = 7.72 cfs @ 12.11 hr 6.79 cfs @ 12.10 hr
Runoff Volume= 22,670 cf 20,507 cf
Source context and notes | Peak Flow Rate = | 25.71 cfs | 20.57 cfs | 23.60 cfs | The projected 100-year post-construction peak flow rate, 23.60 cfs, exceeds the allowable flow rate, 20.57 cfs. Therefore, the project is still not in compliance with the stormwater runoff quantity control requirement under the option found in N.J.A.C. 7:8-5.6(b)3. A stormwater runoff quantity control or green infrastructure BMP will be required to reduce the projected 100-year post-construction peak flow to 80%, or lower, of the pre-construction peak flow rate. # Step 4: Calculate the peak flow rates for other design storms for the pre- and post-construction conditions and compare the hydrographs In Step 3, the comparison of hydrographs for the pre- and post-construction projected 100-year design year storms has shown that a reduction of the impervious surface or runoff volume in a redevelopment project may not comply with N.J.A.C. 7:8-5.6(b). The rules require the demonstration of compliance with the requirements in N.J.A.C. 7:8-5.6(b) for the current and projected 2-, 10- and 100-year storms. Using the same technique in Step 3, a hydrograph comparison of the pre- and post- current 2-year storms, for example, is shown in the table below. To correctly calculate the time of concentration, first $P_{2}$ was calculated by multiplying the NOAA NWQ PFDS rainfall depth for the 2-year storm (3.33 in) with the current precipitation adjustment factor (1.01) and is equal to 3.36 in. Next, the modeling software is used to produce the hydrographs, with the peak flow rates and time intervals exported as data for input into a spreadsheet to create a chart. Here is the summary information. | Current 2-year Design Storm | | | | --- | --- | --- | | Parameter | Pre-Construction Condition | Post-Construction Condition | | Peak Flow Rate & Time of Peak = | 7.72 cfs @ 12.11 hr | 6.79 cfs @ 12.10 hr | | Runoff Volume= | 22,670 cf | 20,507 cf | Pre- and post-condition hydrographs are provided in the chart below. As with those for the projected 100-year storm from Step 3, they appear to be nearly identical.

19. Table 19

BMP 2026, Ch 5, p. 49

Pre-construction Drainage Area Name (cover condition or undisturbed) Area (ac) CN Tc(min) Pre-construction Design Storm Flow Rate (cfs)
2-year 10-year 100-year
Pre-A1 (pasture) 0.25 61 17.4 0.07 0.30 0.88
Pre-A2 (undisturbed) 0.75 61 24.2 0.19 0.78 2.26
Total Pre-A (Hydrograph addition) 1.00 0.26 1.05 3.07
Pre-B1 (warehouse) 0.50 98 2.8 1.76 2.81 4.80
Pre-B2 (woods/grass) 0.25 70 18.6 0.17 0.45 1.07
Total Pre-B (Hydrograph addition) 0.75 1.83 3.03 5.37
Source context and notes Step 2: Stormwater Runoff Quantity Standards: For a major development project, stormwater runoff quantity control is required. The option to demonstrate compliance with N.J.A.C. 7:8-5.6(b)3 is chosen. The peak flow rates for pre-construction condition are calculated as follows: - CN values for the pre-construction condition are chosen based on the land cover having the least runoff potential and assuming good condition rather than fair or poor. The asphalt parking lot cannot be considered to be impervious surface since it has been removed and vegetation has been re-established. - The time of concentration is calculated by using a flow path of sheet flow computed by McCuen-Spiess limitation, plus a segment of shallow concentrated flow based the land cover specified above for the drainage area. The 2-, 10- and 100- year design storms produce rainfall depths, in Ocean County, of 3.4, 5.4 and 9.2 inches, respectively. For this example, the existing condition has two points of analysis: POA-A and POA-B. The times of concentration, volumes and peak flow rates from impervious surfaces and pervious surfaces must be calculated separately and the results are shown in the table below. When subdrainage areas have different times of concentration, the combined flow rate cannot be the sum of the peak flow rates for each of the subdrainage areas. In such an instance, the hydrographs for each of the subdrainage areas must be added, and then the peak flow rate is obtained from the results. | Pre-construction Drainage Area Name (cover condition or undisturbed) | Area (ac) | CN | Tc(min) | Pre-construction Design Storm Flow Rate (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | | | | 2-year | 10-year | 100-year | | Pre-A1 (pasture) | 0.25 | 61 | 17.4 | 0.07 | 0.30 | 0.88 | | Pre-A2 (undisturbed) | 0.75 | 61 | 24.2 | 0.19 | 0.78 | 2.26 | | Total Pre-A (Hydrograph addition) | 1.00 | | | 0.26 | 1.05 | 3.07 | | Pre-B1 (warehouse) | 0.50 | 98 | 2.8 | 1.76 | 2.81 | 4.80 | | Pre-B2 (woods/grass) | 0.25 | 70 | 18.6 | 0.17 | 0.45 | 1.07 | | Total Pre-B (Hydrograph addition) | 0.75 | | | 1.83 | 3.03 | 5.37 | - Allowable post-construction peak flow under N.J.A.C. 7:8-5.6(b)3: Under N.J.A.C. 7:8-5.6(b)3, the post-construction condition peak flow rates must be reduced to 50%, 75% and 80% of the pre-construction peak flow rates, respectively. It is also stated in the rules that the percentages apply only to the post-construction stormwater runoff that is attributable to the portion of the site on which the proposed development or project is to be constructed. Therefore, the reduction percentages are not required for the undisturbed drainage area, Pre-A2. The allowable peak flow rates are listed below.

20. Table 20

BMP 2026, Ch 5, p. 50

Pre-construction Drainage Area Name (cover condition) Area (ac) Allowable Design Storm Peak Flow Rates (cfs)
2-year 10-year 100-year
Pre-A1 (pasture) 0.25 0.04 0.23 0.70
Pre-A2 (undisturbed) 0.75 0.19 0.78 2.26
Total Pre-A 1.00 0.23 1.01 2.96
Pre-B1 (warehouse) 0.50 0.88 2.11 3.84
Pre-B2 (woods/grass) 0.25 0.09 0.34 0.86
Total Pre-B 0.75 0.92 2.27 4.30
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Pre-construction Drainage Area Name (cover condition) | Area (ac) | Allowable Design Storm Peak Flow Rates (cfs) | | | | --- | --- | --- | --- | --- | | | | 2-year | 10-year | 100-year | | Pre-A1 (pasture) | 0.25 | 0.04 | 0.23 | 0.70 | | Pre-A2 (undisturbed) | 0.75 | 0.19 | 0.78 | 2.26 | | Total Pre-A | 1.00 | 0.23 | 1.01 | 2.96 | | Pre-B1 (warehouse) | 0.50 | 0.88 | 2.11 | 3.84 | | Pre-B2 (woods/grass) | 0.25 | 0.09 | 0.34 | 0.86 | | Total Pre-B | 0.75 | 0.92 | 2.27 | 4.30 | The post-construction peak flow rates for each of the proposed drainage areas (prior to the incorporation of stormwater management measures) are shown below: | Post-construction Drainage Area Name (undisturbed/cover condition) | Area (ac) | CN | Tc(min) | Post-construction Design Storm Flow Rate (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | | | | 2-year | 10-year | 100-year | | Post-A1 (parking/ gravel) | 0.25 | 96 | 3.5 | 0.83 | 1.35 | 2.33 | | Post-A2 (undisturbed/pasture) | 0.75 | 61 | 24.2 | 0.19 | 0.78 | 2.26 | | Total Post-A (Hydrograph addition) | 1.00 | | | 0.85 | 1.62 | 3.31 | | Post-B1 (building or walkway) | 0.16 | 98 | 1.6 | 0.57 | 0.90 | 1.54 | | Post-B2 (open space/grass 50% to 75%) | 0.59 | 79 | 8.9 | 0.90 | 1.91 | 3.93 | | Total Post-B (Hydrograph addition) | 0.75 | | | 1.24 | 2.41 | 4.74 | ☐ The uncontrolled post-construction peak flow rates generated by drainage area Post-A exceed the allowable design storm peak flow rates of stormwater runoff generated by drainage area Pre-A. Therefore, green infrastructure BMPs listed in Table 5-1 or 5-2, as required by N.J.A.C. 7:8-5.3(c), must be used to meet the stormwater runoff quantity control requirements. As stated on Page 48, a small-scale infiltration basin is proposed to provide the stormwater runoff quantity control.

21. Table 21

BMP 2026, Ch 5, p. 50

Post-construction Drainage Area Name (undisturbed/cover condition) Area (ac) CN Tc(min) Post-construction Design Storm Flow Rate (cfs)
2-year 10-year 100-year
Post-A1 (parking/ gravel) 0.25 96 3.5 0.83 1.35 2.33
Post-A2 (undisturbed/pasture) 0.75 61 24.2 0.19 0.78 2.26
Total Post-A (Hydrograph addition) 1.00 0.85 1.62 3.31
Post-B1 (building or walkway) 0.16 98 1.6 0.57 0.90 1.54
Post-B2 (open space/grass 50% to 75%) 0.59 79 8.9 0.90 1.91 3.93
Total Post-B (Hydrograph addition) 0.75 1.24 2.41 4.74
Source context and notes | Pre-A2 (undisturbed) | 0.75 | 0.19 | 0.78 | 2.26 | | Total Pre-A | 1.00 | 0.23 | 1.01 | 2.96 | | Pre-B1 (warehouse) | 0.50 | 0.88 | 2.11 | 3.84 | | Pre-B2 (woods/grass) | 0.25 | 0.09 | 0.34 | 0.86 | | Total Pre-B | 0.75 | 0.92 | 2.27 | 4.30 | The post-construction peak flow rates for each of the proposed drainage areas (prior to the incorporation of stormwater management measures) are shown below: | Post-construction Drainage Area Name (undisturbed/cover condition) | Area (ac) | CN | Tc(min) | Post-construction Design Storm Flow Rate (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | | | | 2-year | 10-year | 100-year | | Post-A1 (parking/ gravel) | 0.25 | 96 | 3.5 | 0.83 | 1.35 | 2.33 | | Post-A2 (undisturbed/pasture) | 0.75 | 61 | 24.2 | 0.19 | 0.78 | 2.26 | | Total Post-A (Hydrograph addition) | 1.00 | | | 0.85 | 1.62 | 3.31 | | Post-B1 (building or walkway) | 0.16 | 98 | 1.6 | 0.57 | 0.90 | 1.54 | | Post-B2 (open space/grass 50% to 75%) | 0.59 | 79 | 8.9 | 0.90 | 1.91 | 3.93 | | Total Post-B (Hydrograph addition) | 0.75 | | | 1.24 | 2.41 | 4.74 | ☐ The uncontrolled post-construction peak flow rates generated by drainage area Post-A exceed the allowable design storm peak flow rates of stormwater runoff generated by drainage area Pre-A. Therefore, green infrastructure BMPs listed in Table 5-1 or 5-2, as required by N.J.A.C. 7:8-5.3(c), must be used to meet the stormwater runoff quantity control requirements. As stated on Page 48, a small-scale infiltration basin is proposed to provide the stormwater runoff quantity control. ☐ Similarly, for drainage area B, the uncontrolled post-construction peak flow rates of stormwater runoff generated by drainage area Post-B exceed the allowable design storm peak flow rates of stormwater runoff generated by drainage area Pre-B. Therefore, green infrastructure BMPs listed in Table 5-1 or 5-2 must also be used to meet the stormwater runoff quantity control requirements.

22. Table 22

BMP 2026, Ch 5, p. 51

Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 2.95" for 2-Year event
Inflow = 0.83 cfs @ 12.09 hrs, Volume= 2,674 cf
Outflow = 0.12 cfs @ 12.57 hrs, Volume= 2,674 cf, Atten= 85%, Lag= 28.8 min
Discarded = 0.09 cfs @ 11.60 hrs, Volume= 2,532 cf
Primary = 0.03 cfs @ 12.57 hrs, Volume= 142 cf
Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs
Peak Elev= 0.29' @ 12.57 hrs Surf.Area= 2,700 sf Storage= 777 cf
Plug-Flow detention time= 51.7 min calculated for 2,674 cf (100% of inflow)
Center-of-Mass det. time= 51.6 min (825.1 - 773.5)
Volume Invert Avail.Storage Storage Description
#1 0.00' 8,100 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cumulative
(feet) (sq-ft) (cubic-feet) (cubic-feet)
0.00 2,700 0 0
1.00 2,700 2,700 2,700
2.00 2,700 2,700 5,400
3.00 2,700 2,700 8,100
Device Routing Invert Outlet Devices
#1 Primary 1.00' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir
Head (feet) 0.20 0.40 0.60 0.80 1.00
Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Primary 0.15' 2.5" Vert. Orifice/Grate C= 0.600
#3 Discarded 0.00' 1.50 in/hr Exfiltration over Surface area
Discarded OutFlow Max=0.09 cfs @ 11.60 hrs HW=0.03' (Free Discharge)
←3=Exfiltration (Exfiltration Controls 0.09 cfs)
Primary OutFlow Max=0.03 cfs @ 12.57 hrs HW=0.29' (Free Discharge)
←1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)
←2=Orifice/Grate (Orifice Controls 0.03 cfs @ 1.26 fps)
Source context and notes Source revision: January 2026. # Step 3: Calculate the Post-Construction Design Storm Peak Flow Rates for Drainage Area Post-A-1 The proposed small-scale infiltration basin has a 2,700 sf bottom footprint and a basin depth of 2 ft, plus 1 ft of freeboard. The 4-sided concrete outlet structure includes a 2.5 in orifice located 0.15 ft above the basin bottom and a top grate, which acts as a broad-crested weir, located 1 ft above the basin bottom. The weir opening is 20 ft long = 4 sides x 5 ft per side, and the depth of the weir, i.e., the outlet structure wall thickness, is 0.5 ft. Exfiltration is included in the routing calculation, using the design permeability rate of 1.5 in/hr, which is one-half of the tested permeability rate of 3 in/hr. Take note that the exfiltration can be credited only on the infiltration area, which is the footprint of the BMP. The side slopes of the BMP cannot be used for exfiltration. Therefore, the routing, with exfiltration, must only use the design permeability rate of the most restrictive soil layer under the BMP and the footprint, i.e., the exfiltration area, of the BMP to determine the maximum exfiltration flow rate (cfs) in the BMP. In the current case, however, the BMP has the same surface area 2,700 sf from the bottom to the top. A constant exfiltration flow rate, 0.09375 cfs (2,700 sf x 1.5 in/hr x 1/12 in/ft x 1/3600 second/hr), in the routing or a constant exfiltration rate 1.5 in/hr is applied to 2,700 sf for all water elevations in the routing. The results obtained from HydroCAD® are each shown on the following pages for the 2-, 10- and 100-year design storms. A designer may use other hydrologic - hydraulic modeling software to perform the routing calculations. ## 2-year Design Storm Post-Construction Condition Summary Report | Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 2.95" for 2-Year event | | | | | | --- | --- | --- | --- | --- | | Inflow = 0.83 cfs @ 12.09 hrs, Volume= 2,674 cf | | | | | | Outflow = 0.12 cfs @ 12.57 hrs, Volume= 2,674 cf, Atten= 85%, Lag= 28.8 min | | | | | | Discarded = 0.09 cfs @ 11.60 hrs, Volume= 2,532 cf | | | | | | Primary = 0.03 cfs @ 12.57 hrs, Volume= 142 cf | | | | | | Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs | | | | | | Peak Elev= 0.29' @ 12.57 hrs Surf.Area= 2,700 sf Storage= 777 cf | | | | | | Plug-Flow detention time= 51.7 min calculated for 2,674 cf (100% of inflow) | | | | | | Center-of-Mass det. time= 51.6 min (825.1 - 773.5) | | | | | | Volume Invert Avail.Storage Storage Description | | | | | | #1 0.00' 8,100 cf Custom Stage Data (Prismatic) Listed below (Recalc) | | | | | | Elevation Surf.Area Inc.Store Cumulative | | | | | | (feet) (sq-ft) (cubic-feet) (cubic-feet) | | | | | | 0.00 | 2,700 | 0 | 0 | | | 1.00 | 2,700 | 2,700 | 2,700 | | | 2.00 | 2,700 | 2,700 | 5,400 | | | 3.00 | 2,700 | 2,700 | 8,100 | | | Device Routing Invert Outlet Devices | | | | | | #1 Primary 1.00' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir | | | | | | Head (feet) 0.20 0.40 0.60 0.80 1.00 | | | | | | Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | | | | #2 Primary 0.15' 2.5" Vert. Orifice/Grate C= 0.600 | | | | | | #3 Discarded 0.00' 1.50 in/hr Exfiltration over Surface area | | | | | | Discarded OutFlow Max=0.09 cfs @ 11.60 hrs HW=0.03' (Free Discharge) | | | | | | ←3=Exfiltration (Exfiltration Controls 0.09 cfs) | | | | | | Primary OutFlow Max=0.03 cfs @ 12.57 hrs HW=0.29' (Free Discharge) | | | | | | ←1=Broad-Crested Rectangular Weir (Controls 0.00 cfs) | | | | | | ←2=Orifice/Grate (Orifice Controls 0.03 cfs @ 1.26 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission.

23. Table 23

BMP 2026, Ch 5, p. 52

Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 4.93" for 10-Year event
Inflow = 1.35 cfs @ 12.09 hrs, Volume= 4,474 cf
Outflow = 0.18 cfs @ 12.62 hrs, Volume= 4,474 cf, Atten= 87%, Lag= 31.7 min
Discarded = 0.09 cfs @ 11.10 hrs, Volume= 3,672 cf
Primary = 0.09 cfs @ 12.62 hrs, Volume= 802 cf
Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs
Peak Elev= 0.54' @ 12.62 hrs Surf.Area= 2,700 sf Storage= 1,451 cf
Plug-Flow detention time= 72.0 min calculated for 4,470 cf (100% of inflow)
Center-of-Mass det. time= 72.0 min (832.6 - 760.6)
Volume Invert Avail.Storage Storage Description
#1 0.00' 8,100 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet)
0.00 2,700 0 0
1.00 2,700 2,700 2,700
2.00 2,700 2,700 5,400
3.00 2,700 2,700 8,100
Device Routing Invert Outlet Devices
#1 Primary 1.00' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir
Head (feet) 0.20 0.40 0.60 0.80 1.00
Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Primary 0.15' 2.5" Vert. Orifice/Grate C= 0.600
#3 Discarded 0.00' 1.50 in/hr Exfiltration over Surface area
Discarded OutFlow Max=0.09 cfs @ 11.10 hrs HW=0.03' (Free Discharge)
3=Exfiltration (Exfiltration Controls 0.09 cfs)
Primary OutFlow Max=0.09 cfs @ 12.62 hrs HW=0.54' (Free Discharge)
1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)
2=Orifice/Grate (Orifice Controls 0.09 cfs @ 2.56 fps)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. # 10-year Design Storm Post-Construction Condition Summary Report | Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 4.93" for 10-Year event | | | | | | --- | --- | --- | --- | --- | | Inflow = 1.35 cfs @ 12.09 hrs, Volume= 4,474 cf | | | | | | Outflow = 0.18 cfs @ 12.62 hrs, Volume= 4,474 cf, Atten= 87%, Lag= 31.7 min | | | | | | Discarded = 0.09 cfs @ 11.10 hrs, Volume= 3,672 cf | | | | | | Primary = 0.09 cfs @ 12.62 hrs, Volume= 802 cf | | | | | | Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs | | | | | | Peak Elev= 0.54' @ 12.62 hrs Surf.Area= 2,700 sf Storage= 1,451 cf | | | | | | Plug-Flow detention time= 72.0 min calculated for 4,470 cf (100% of inflow) | | | | | | Center-of-Mass det. time= 72.0 min (832.6 - 760.6) | | | | | | Volume | Invert | Avail.Storage | Storage Description | | | #1 | 0.00' | 8,100 cf | Custom Stage Data (Prismatic) Listed below (Recalc) | | | Elevation (feet) | Surf.Area (sq-ft) | Inc.Store (cubic-feet) | Cum.Store (cubic-feet) | | | 0.00 | 2,700 | 0 | 0 | | | 1.00 | 2,700 | 2,700 | 2,700 | | | 2.00 | 2,700 | 2,700 | 5,400 | | | 3.00 | 2,700 | 2,700 | 8,100 | | | Device | Routing | Invert | Outlet Devices | | | #1 | Primary | 1.00' | 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir
Head (feet) 0.20 0.40 0.60 0.80 1.00
Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | #2 | Primary | 0.15' | 2.5" Vert. Orifice/Grate C= 0.600 | | | #3 | Discarded | 0.00' | 1.50 in/hr Exfiltration over Surface area | | | Discarded OutFlow Max=0.09 cfs @ 11.10 hrs HW=0.03' (Free Discharge)
3=Exfiltration (Exfiltration Controls 0.09 cfs) | | | | | | Primary OutFlow Max=0.09 cfs @ 12.62 hrs HW=0.54' (Free Discharge)
1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)
2=Orifice/Grate (Orifice Controls 0.09 cfs @ 2.56 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission.

24. Table 24

BMP 2026, Ch 5, p. 53

Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 8.72" for 100-Year event
Inflow = 2.33 cfs @ 12.09 hrs, Volume= 7,912 cf
Outflow = 0.45 cfs @ 12.42 hrs, Volume= 7,912 cf, Atten= 81%, Lag= 19.7 min
Discarded = 0.09 cfs @ 10.00 hrs, Volume= 5,296 cf
Primary = 0.36 cfs @ 12.42 hrs, Volume= 2,616 cf
Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs
Peak Elev= 1.02' @ 12.40 hrs Surf.Area= 2,700 sf Storage= 2,762 cf
Plug-Flow detention time= 103.3 min calculated for 7,904 cf (100% of inflow)
Center-of-Mass det. time= 103.2 min (852.1 - 748.9)
Volume Invert Avail.Storage Storage Description
#1 0.00' 8,100 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet)
0.00 2,700 0 0
1.00 2,700 2,700 2,700
2.00 2,700 2,700 5,400
3.00 2,700 2,700 8,100
Device Routing Invert Outlet Devices
#1 Primary 1.00' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Primary 0.15' 2.5" Vert. Orifice/Grate C= 0.600
#3 Discarded 0.00' 1.50 in/hr Exfiltration over Surface area
Discarded OutFlow Max=0.09 cfs @ 10.00 hrs HW=0.03' (Free Discharge) -3=Exfiltration (Exfiltration Controls 0.09 cfs)
Primary OutFlow Max=0.34 cfs @ 12.42 hrs HW=1.02' (Free Discharge) -1=Broad-Crested Rectangular Weir (Weir Controls 0.20 cfs @ 0.43 fps) -2=Orifice/Grate (Orifice Controls 0.14 cfs @ 4.22 fps)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. # 100-year Design Storm Post-Construction Condition Summary Report | Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 8.72" for 100-Year event | | | | | | --- | --- | --- | --- | --- | | Inflow = 2.33 cfs @ 12.09 hrs, Volume= 7,912 cf | | | | | | Outflow = 0.45 cfs @ 12.42 hrs, Volume= 7,912 cf, Atten= 81%, Lag= 19.7 min | | | | | | Discarded = 0.09 cfs @ 10.00 hrs, Volume= 5,296 cf | | | | | | Primary = 0.36 cfs @ 12.42 hrs, Volume= 2,616 cf | | | | | | Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs | | | | | | Peak Elev= 1.02' @ 12.40 hrs Surf.Area= 2,700 sf Storage= 2,762 cf | | | | | | Plug-Flow detention time= 103.3 min calculated for 7,904 cf (100% of inflow) | | | | | | Center-of-Mass det. time= 103.2 min (852.1 - 748.9) | | | | | | Volume | Invert | Avail.Storage | Storage Description | | | #1 | 0.00' | 8,100 cf | Custom Stage Data (Prismatic) Listed below (Recalc) | | | Elevation (feet) | Surf.Area (sq-ft) | Inc.Store (cubic-feet) | Cum.Store (cubic-feet) | | | 0.00 | 2,700 | 0 | 0 | | | 1.00 | 2,700 | 2,700 | 2,700 | | | 2.00 | 2,700 | 2,700 | 5,400 | | | 3.00 | 2,700 | 2,700 | 8,100 | | | Device | Routing | Invert | Outlet Devices | | | #1 | Primary | 1.00' | 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | #2 | Primary | 0.15' | 2.5" Vert. Orifice/Grate C= 0.600 | | | #3 | Discarded | 0.00' | 1.50 in/hr Exfiltration over Surface area | | | Discarded OutFlow Max=0.09 cfs @ 10.00 hrs HW=0.03' (Free Discharge) -3=Exfiltration (Exfiltration Controls 0.09 cfs) | | | | | | Primary OutFlow Max=0.34 cfs @ 12.42 hrs HW=1.02' (Free Discharge) -1=Broad-Crested Rectangular Weir (Weir Controls 0.20 cfs @ 0.43 fps) -2=Orifice/Grate (Orifice Controls 0.14 cfs @ 4.22 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. The post-construction peak flow discharges from the proposed small-scale infiltration basin, which are labeled "Primary" flow rates in the above listed reports, were calculated to be 0.03, 0.09 and 0.36 cfs for the 2-, 10- and 100-year design storms, respectively. Adding the hydrograph to the corresponding flow rates generated by the undisturbed drainage area Post-A2, yields the total calculated peak flow rates of Post-A drainage area: 0.19, 0.78 and 2.26 cfs for the 2-, 10- and 100-year design storms, respectively. The table on the following page compares the allowable design storm peak flow rates for the post-construction condition for Post-A drainage area at point of analysis A to those calculated for the post-construction condition to check whether the design meets the requirement to reduce the peak flow rates, respectively, to 50, 75 and 80% of the pre-construction peak flow rates.

25. Table 25

BMP 2026, Ch 5, p. 54

Post-construction Drainage Area Designation Allowable Design Storm Peak Flow Rate (cfs) Design Storm Peak Flow Rates with one Small-Scale Infiltration Basin (cfs)
2-year 10-year 100-year 2-year 10-year 100-year
Post-A1 (parking lot/ gravel) 0.04 0.23 0.70 0.03 0.09 0.36
Post-A2 (undisturbed area/ pasture) 0.19 0.78 2.26 0.19 0.78 2.26
Post-A 0.23 1.01 2.96 0.22 0.86 2.57
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. The post-construction peak flow rates for each of the proposed drainage areas are shown below (after the incorporation of stormwater management measures). | Post-construction Drainage Area Designation | Allowable Design Storm Peak Flow Rate (cfs) | | | Design Storm Peak Flow Rates with one Small-Scale Infiltration Basin (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | 2-year | 10-year | 100-year | | Post-A1 (parking lot/ gravel) | 0.04 | 0.23 | 0.70 | 0.03 | 0.09 | 0.36 | | Post-A2 (undisturbed area/ pasture) | 0.19 | 0.78 | 2.26 | 0.19 | 0.78 | 2.26 | | Post-A | 0.23 | 1.01 | 2.96 | 0.22 | 0.86 | 2.57 | # Step 4: Perform the Required Groundwater Mounding Analysis The design of the small-scale infiltration basin must include a groundwater mounding analysis to verify the drain time within 72 hours and whether there is an adverse hydraulic impact to the groundwater level due to the infiltration practice, in accordance with N.J.A.C. 7:8-5.2(h). The NJDEP Hantush Spreadsheet is used for the groundwater mounding analysis for which guidance is included in Chapter 13 of this manual. For this example, the small-scale infiltration basin measures 52 ft by 52 ft. The recharge rate, R, is the design permeability rate, which is one half the tested permeability rate, and equals $0.5 \times 3.0 \mathrm{in/hr} = 1.5 \mathrm{in/hr}$ . The parameters for specific yield, $S_{\mathrm{y}}$ , and the horizontal hydraulic conductivity, Kh, will be set at the default values specified in Chapter 13. The horizontal hydraulic conductivity rate is 5 times the recharge rate since the site, located in Ocean County, is in the Coastal Plain. The x and y values are equal to half of the respective basin dimensions.

26. Table 26

BMP 2026, Ch 5, p. 55

Input Values
1.50 R Recharge rate (permeability rate) (in/hr)
0.150 Sy Specific yield, Sy (dimensionless)
default value is 0.15; max value is 0.2 provided that a lab test data is submitted
7.50 Kh Horizontal hydraulic conductivity (in/hr)
Kh = 5xRecharge Rate (B) in the coastal plain: Kh=R outside the coastal plain
26.000 x 1/2 length of basin (x direction, in feet)
26.000 y 1/2 width of basin (y direction, in feet)
15.69 t Duration of infiltration period (hours)
10.000 hi(0) Initial thickness of saturated zone (feet)
16.26 h(max) Maximum thickness of saturated zone (beneath center of basin at end of infiltration period)
6.26 Δh(max) Maximum groundwater mounding (beneath center of basin at end of infiltration period)
Ground-water Mounding, in feet Distance from center of basin in x direction, in feet
6.259 0 Re-Calculate Now
5.991 10
5.123 20
5.558 30
2.206 40
1.287 50
0.710 60
0.572 70
0.186 80
0.093 90
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Duration of infiltration period, $t(hr) = \frac{\text{Discarded Volume via Exfiltration (cf)} \times 12 \text{ in}/ft}{\text{Infiltration area (sf)} \times \text{Exfiltration rate (in/hr)}} = \frac{5,296 \text{ cf} \times 12 \text{ in}/ft}{2,700 \text{ sf} \times 1.5 \text{ in/hr}} = 15.69 \text{ hr}$ The initial thickness of the saturated zone, $hi(0)$, is set at the default value. Clicking on the blue button labeled "Re-Calculate Now" produced the results depicted below. | Input Values | | | | | | | | | | | | | | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | | 1.50 | R | Recharge rate (permeability rate) (in/hr) | | | | | | | | | | | | 0.150 | Sy | Specific yield, Sy (dimensionless) | | | | | | | | | | | | | | default value is 0.15; max value is 0.2 provided that a lab test data is submitted | | | | | | | | | | | | 7.50 | Kh | Horizontal hydraulic conductivity (in/hr) | | | | | | | | | | | | | | Kh = 5xRecharge Rate (B) in the coastal plain: Kh=R outside the coastal plain | | | | | | | | | | | | 26.000 | x | 1/2 length of basin (x direction, in feet) | | | | | | | | | | | | 26.000 | y | 1/2 width of basin (y direction, in feet) | | | | | | | | | | | | 15.69 | t | Duration of infiltration period (hours) | | | | | | | | | | | | 10.000 | hi(0) | Initial thickness of saturated zone (feet) | | | | | | | | | | | | | | | | | | | | | | | | | | 16.26 | h(max) | Maximum thickness of saturated zone (beneath center of basin at end of infiltration period) | | | | | | | | | | | | 6.26 | Δh(max) | Maximum groundwater mounding (beneath center of basin at end of infiltration period) | | | | | | | | | | | | Ground-water Mounding, in feet | Distance from center of basin in x direction, in feet | | | | | | | | | | | | | 6.259 | 0 | Re-Calculate Now | | | | | | | | | | | | 5.991 | 10 | | | | | | | | | | | | | 5.123 | 20 | | | | | | | | | | | | | 5.558 | 30 | | | | | | | | | | | | | 2.206 | 40 | | | | | | | | | | | | | 1.287 | 50 | | | | | | | | | | | | | 0.710 | 60 | | | | | | | | | | | | | 0.572 | 70 | | | | | | | | | | | | | 0.186 | 80 | | | | | | | | | | | | | 0.093 | 90 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | The results show that the maximum height of the groundwater mounding, $\Delta h(\max)$, is 6.26 ft. Since the groundwater table is 8 ft below the existing ground elevation, the elevated groundwater table will be 1.74 ft below the existing ground level at the center of the small-scale infiltration basin at the moment all of the stormwater runoff has infiltrated into the sand layer. However, the proposed small-scale basin provides 2 ft of temporary storage for stormwater, as depicted above by the light blue rectangle. The basin also includes a sand layer that is 0.5 ft deep, shown in tan. The bottom surface of the BMP is 2.0 ft below the existing ground elevation. Since the elevated groundwater table will be only 1.74 ft below the existing ground elevation, the elevated groundwater level will have an adverse impact on the drainage of the basin. Since there is an adverse impact on the drainage of the basin, the rate of exfiltration will also be impacted, meaning the ability of the basin to drain will be reduced. A smaller recharge rate must be

27. Table 27

BMP 2026, Ch 5, p. 57

Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 8.72" for 100-Year event
Inflow = 2.31 cfs @ 12.10 hrs, Volume= 7,912 cf
Outflow = 0.65 cfs @ 12.30 hrs, Volume= 7,912 cf, Atten= 72%, Lag= 11.8 min
Discarded = 0.07 cfs @ 9.28 hrs, Volume= 4,603 cf
Primary = 0.58 cfs @ 12.30 hrs, Volume= 3,309 cf
Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
Peak Elev= 1.04' @ 12.30 hrs Surf Area= 2,700 sf Storage= 2,802 cf
Plug-Flow detention time= 124.3 min calculated for 7,912 cf (100% of inflow)
Center-of-Mass det. time= 124.1 min (873.0 - 748.9)
Volume Invert Avail Storage Storage Description
#1 0.00' 8,100 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation (feet) Surf Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet)
0.00 2,700 0 0
1.00 2,700 2,700 2,700
2.00 2,700 2,700 5,400
3.00 2,700 2,700 8,100
Device Routing Invert Outlet Devices
#1 Primary 1.00' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir
Head (feet) 0.20 0.40 0.60 0.80 1.00
Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Primary 0.15' 2.5" Vert. Orifice/Grate C= 0.600
#3 Discarded 0.00' 1.10 in/hr Exfiltration over Surface area
Discarded OutFlow Max=0.07 cfs @ 9.28 hrs HW=0.03' (Free Discharge)
-3=Exfiltration (Exfiltration Controls 0.07 cfs)
Primary OutFlow Max=0.54 cfs @ 12.30 hrs HW=1.04' (Free Discharge)
-1=Broad-Crested Rectangular Weir (Weir Controls 0.40 cfs @ 0.54 fps)
-2=Orifice/Grate (Orifice Controls 0.15 cfs @ 4.26 fps)
Source context and notes - Based on the methodology discussed above, the trial and error approach for the current example is as follows: a. Reduce the recharge rate from 1.5 in/hr to 1.1 in/hr. b. The exfiltration rate used in the new basin routing calculation equals the recharge rate from Step a. The results are shown in the image below: Revised 100-year Design Storm Post-Construction Condition Summary Report Exfiltration = 1.1 in/hr | Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 8.72" for 100-Year event | | | | | | --- | --- | --- | --- | --- | | Inflow = 2.31 cfs @ 12.10 hrs, Volume= 7,912 cf | | | | | | Outflow = 0.65 cfs @ 12.30 hrs, Volume= 7,912 cf, Atten= 72%, Lag= 11.8 min | | | | | | Discarded = 0.07 cfs @ 9.28 hrs, Volume= 4,603 cf | | | | | | Primary = 0.58 cfs @ 12.30 hrs, Volume= 3,309 cf | | | | | | Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs | | | | | | Peak Elev= 1.04' @ 12.30 hrs Surf Area= 2,700 sf Storage= 2,802 cf | | | | | | Plug-Flow detention time= 124.3 min calculated for 7,912 cf (100% of inflow) | | | | | | Center-of-Mass det. time= 124.1 min (873.0 - 748.9) | | | | | | Volume Invert Avail Storage Storage Description | | | | | | #1 0.00' 8,100 cf Custom Stage Data (Prismatic) Listed below (Recalc) | | | | | | Elevation (feet) Surf Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet) | | | | | | 0.00 | 2,700 | 0 | 0 | | | 1.00 | 2,700 | 2,700 | 2,700 | | | 2.00 | 2,700 | 2,700 | 5,400 | | | 3.00 | 2,700 | 2,700 | 8,100 | | | Device Routing Invert Outlet Devices | | | | | | #1 Primary 1.00' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir | | | | | | | | Head (feet) 0.20 0.40 0.60 0.80 1.00 | | | | | | Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | | #2 Primary 0.15' 2.5" Vert. Orifice/Grate C= 0.600 | | | | | | #3 Discarded 0.00' 1.10 in/hr Exfiltration over Surface area | | | | | | Discarded OutFlow Max=0.07 cfs @ 9.28 hrs HW=0.03' (Free Discharge) | | | | | | -3=Exfiltration (Exfiltration Controls 0.07 cfs) | | | | | | Primary OutFlow Max=0.54 cfs @ 12.30 hrs HW=1.04' (Free Discharge) | | | | | | -1=Broad-Crested Rectangular Weir (Weir Controls 0.40 cfs @ 0.54 fps) | | | | | | -2=Orifice/Grate (Orifice Controls 0.15 cfs @ 4.26 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. The 100-year storm routing calculation shows the exfiltration (discarded) volume is reduced from 5,296 cf at an exfiltration rate of 1.5 in/hr to 4,603 cf at 1.1 in/hr. The peak flow rate (primary) from the proposed small-scale infiltration basin (Post-A1) is increased from 0.36 cfs to 0.58 cfs and must be added to the flow from Post-A2 (undisturbed area/ pasture). The new value for the combined peak flow rate by hydrograph addition is 2.81 cfs, which does not exceed the allowable design storm peak flow rate, 2.96 cfs, for the Post-A drainage area. i. The peak flow rates for 2- and 10-year design storms from the small-scale infiltration basin are calculated and the results are shown below:

28. Table 28

BMP 2026, Ch 5, p. 58

Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 2.95" for 2-Year event
Inflow = 0.84 cfs @ 12.10 hrs, Volume= 2,674 cf
Outflow = 0.11 cfs @ 12.62 hrs, Volume= 2,674 cf, Atten= 87%, Lag= 31.4 min
Discarded = 0.07 cfs @ 11.36 hrs, Volume= 2,395 cf
Primary = 0.04 cfs @ 12.62 hrs, Volume= 279 cf
Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
Peak Elev= 0.32' @ 12.62 hrs Surf.Area= 2,700 sf Storage= 877 cf
Plug-Flow detention time= 75.8 min calculated for 2,672 cf (100% of inflow)
Center-of-Mass det. time= 75.8 min (849.3 - 773.5)
Volume Invert Avail.Storage Storage Description
#1 0.00' 8,100 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet)
0.00 2,700 0 0
1.00 2,700 2,700 2,700
2.00 2,700 2,700 5,400
3.00 2,700 2,700 8,100
Device Routing Invert Outlet Devices
#1 Primary 1.00' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir
Head (feet) 0.20 0.40 0.60 0.80 1.00
Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Primary 0.15' 2.5" Vert. Orifice/Grate C= 0.600
#3 Discarded 0.00' 1.10 in/hr Exfiltration over Surface area
Discarded OutFlow Max=0.07 cfs @ 11.36 hrs HW=0.03' (Free Discharge)
-3=Exfiltration (Exfiltration Controls 0.07 cfs)
Primary OutFlow Max=0.04 cfs @ 12.62 hrs HW=0.32' (Free Discharge)
-1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)
-2=Orifice/Grate (Orifice Controls 0.04 cfs @ 1.42 fps)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. # Revised 2-year Design Storm Post-Construction Condition Summary Report Exfiltration = 1.1 in/hr and Basin Footprint Remains = 2,700 sf | Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 2.95" for 2-Year event | | | | | | --- | --- | --- | --- | --- | | Inflow = 0.84 cfs @ 12.10 hrs, Volume= 2,674 cf | | | | | | Outflow = 0.11 cfs @ 12.62 hrs, Volume= 2,674 cf, Atten= 87%, Lag= 31.4 min | | | | | | Discarded = 0.07 cfs @ 11.36 hrs, Volume= 2,395 cf | | | | | | Primary = 0.04 cfs @ 12.62 hrs, Volume= 279 cf | | | | | | Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs | | | | | | Peak Elev= 0.32' @ 12.62 hrs Surf.Area= 2,700 sf Storage= 877 cf | | | | | | Plug-Flow detention time= 75.8 min calculated for 2,672 cf (100% of inflow) | | | | | | Center-of-Mass det. time= 75.8 min (849.3 - 773.5) | | | | | | Volume | Invert | Avail.Storage | Storage Description | | | #1 | 0.00' | 8,100 cf | Custom Stage Data (Prismatic) Listed below (Recalc) | | | Elevation (feet) | Surf.Area (sq-ft) | Inc.Store (cubic-feet) | Cum.Store (cubic-feet) | | | 0.00 | 2,700 | 0 | 0 | | | 1.00 | 2,700 | 2,700 | 2,700 | | | 2.00 | 2,700 | 2,700 | 5,400 | | | 3.00 | 2,700 | 2,700 | 8,100 | | | Device | Routing | Invert | Outlet Devices | | | #1 | Primary | 1.00' | 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir
Head (feet) 0.20 0.40 0.60 0.80 1.00
Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | #2 | Primary | 0.15' | 2.5" Vert. Orifice/Grate C= 0.600 | | | #3 | Discarded | 0.00' | 1.10 in/hr Exfiltration over Surface area | | | Discarded OutFlow Max=0.07 cfs @ 11.36 hrs HW=0.03' (Free Discharge)
-3=Exfiltration (Exfiltration Controls 0.07 cfs) | | | | | | Primary OutFlow Max=0.04 cfs @ 12.62 hrs HW=0.32' (Free Discharge)
-1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)
-2=Orifice/Grate (Orifice Controls 0.04 cfs @ 1.42 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission.

29. Table 29

BMP 2026, Ch 5, p. 59

Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 4.93" for 10-Year event
Inflow = 1.34 cfs @ 12.10 hrs, Volume= 4,474 cf
Outflow = 0.16 cfs @ 12.73 hrs, Volume= 4,474 cf, Atten= 88%, Lag= 37.6 min
Discarded = 0.07 cfs @ 10.72 hrs, Volume= 3,351 cf
Primary = 0.10 cfs @ 12.73 hrs, Volume= 1,123 cf
Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs
Peak Elev= 0.60' @ 12.73 hrs Surf.Area= 2,700 sf Storage= 1,607 cf
Plug-Flow detention time= 98.7 min calculated for 4,471 cf (100% of inflow)
Center-of-Mass det. time= 98.6 min (859.2 - 760.6)
Volume Invert Avail.Storage Storage Description
#1 0.00' 8,100 cf Custom Stage Data (Prismatic) Listed below (Recalc)
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet)
0.00 2,700 0 0
1.00 2,700 2,700 2,700
2.00 2,700 2,700 5,400
3.00 2,700 2,700 8,100
Device Routing Invert Outlet Devices
#1 Primary 1.00' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Primary 0.15' 2.5" Vert. Orifice/Grate C= 0.600
#3 Discarded 0.00' 1.10 in/hr Exfiltration over Surface area
Discarded OutFlow Max=0.07 cfs @ 10.72 hrs HW=0.03' (Free Discharge)3=Exfiltration (Exfiltration Controls 0.07 cfs)
Primary OutFlow Max=0.10 cfs @ 12.73 hrs HW=0.60' (Free Discharge)1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)2=Orifice/Grate (Orifice Controls 0.10 cfs @ 2.81 fps)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Revised 10-year Design Storm Post-Construction Condition Summary Report Exfiltration = 1.1 in/hr and Basin Footprint Remains = 2,700 sf | Inflow Area = 10,890 sf, 0.00% Impervious, Inflow Depth = 4.93" for 10-Year event | | | | | | --- | --- | --- | --- | --- | | Inflow = 1.34 cfs @ 12.10 hrs, Volume= 4,474 cf | | | | | | Outflow = 0.16 cfs @ 12.73 hrs, Volume= 4,474 cf, Atten= 88%, Lag= 37.6 min | | | | | | Discarded = 0.07 cfs @ 10.72 hrs, Volume= 3,351 cf | | | | | | Primary = 0.10 cfs @ 12.73 hrs, Volume= 1,123 cf | | | | | | Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.04 hrs | | | | | | Peak Elev= 0.60' @ 12.73 hrs Surf.Area= 2,700 sf Storage= 1,607 cf | | | | | | Plug-Flow detention time= 98.7 min calculated for 4,471 cf (100% of inflow) | | | | | | Center-of-Mass det. time= 98.6 min (859.2 - 760.6) | | | | | | Volume | Invert | Avail.Storage | Storage Description | | | #1 | 0.00' | 8,100 cf | Custom Stage Data (Prismatic) Listed below (Recalc) | | | Elevation (feet) | Surf.Area (sq-ft) | Inc.Store (cubic-feet) | Cum.Store (cubic-feet) | | | 0.00 | 2,700 | 0 | 0 | | | 1.00 | 2,700 | 2,700 | 2,700 | | | 2.00 | 2,700 | 2,700 | 5,400 | | | 3.00 | 2,700 | 2,700 | 8,100 | | | Device | Routing | Invert | Outlet Devices | | | #1 | Primary | 1.00' | 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir Head (feet) 0.20 0.40 0.60 0.80 1.00 Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | #2 | Primary | 0.15' | 2.5" Vert. Orifice/Grate C= 0.600 | | | #3 | Discarded | 0.00' | 1.10 in/hr Exfiltration over Surface area | | | Discarded OutFlow Max=0.07 cfs @ 10.72 hrs HW=0.03' (Free Discharge)3=Exfiltration (Exfiltration Controls 0.07 cfs) | | | | | | Primary OutFlow Max=0.10 cfs @ 12.73 hrs HW=0.60' (Free Discharge)1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)2=Orifice/Grate (Orifice Controls 0.10 cfs @ 2.81 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. ii. A summary of design storm peak flow rates for two-, 10- and 100-year design storms are shown below: Post-construction Peak Flow Rates of Drainage Area Post-A, with the Incorporation of a Green Infrastructure BMP (1.1 in/hr Exfiltration Rate)

30. Table 30

BMP 2026, Ch 5, p. 59

Post-construction Drainage Area Designation Allowable Design Storm Peak Flow Rate (cfs) Design Storm Peak Flow Rates with a Small-Scale Infiltration Basin (cfs)
2-year 10-year 100-year 2-year 10-year 100-year
Post-A1 (parking lot/ gravel) 0.04 0.23 0.70 0.04 0.10 0.58
Post-A2 (undisturbed area/ pasture) 0.19 0.78 2.26 0.19 0.78 2.26
Post-A 0.23 1.01 2.96 0.23 0.87 2.80
Source context and notes | Primary OutFlow Max=0.10 cfs @ 12.73 hrs HW=0.60' (Free Discharge)1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)2=Orifice/Grate (Orifice Controls 0.10 cfs @ 2.81 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. ii. A summary of design storm peak flow rates for two-, 10- and 100-year design storms are shown below: Post-construction Peak Flow Rates of Drainage Area Post-A, with the Incorporation of a Green Infrastructure BMP (1.1 in/hr Exfiltration Rate) | Post-construction Drainage Area Designation | Allowable Design Storm Peak Flow Rate (cfs) | | | Design Storm Peak Flow Rates with a Small-Scale Infiltration Basin (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | 2-year | 10-year | 100-year | | Post-A1 (parking lot/ gravel) | 0.04 | 0.23 | 0.70 | 0.04 | 0.10 | 0.58 | | Post-A2 (undisturbed area/ pasture) | 0.19 | 0.78 | 2.26 | 0.19 | 0.78 | 2.26 | | Post-A | 0.23 | 1.01 | 2.96 | 0.23 | 0.87 | 2.80 |

31. Table 31

BMP 2026, Ch 5, p. 61

Drainage Area Name Pre-construction Design Storm Flow Rate (cfs) Post-construction Design Storm Flow Rate (cfs)
2-year 10-year 100-year 2-year 10-year 100-year
Post-B1 (building or walkway) 1.76 2.81 4.80 0.57 0.90 1.54
Post-B2 (open space/grass > 75% and woods) 0.17 0.45 1.07 0.90 1.91 3.93
Total Post-B (Hydrograph addition) 1.83 3.03 5.37 1.24 2.41 4.74
Source context and notes ## Step 5: Since the option to meet the Stormwater Runoff Quantity Standards of N.J.A.C. 7:8-5.6(b)3 was selected in Step 2, Determine Whether the Post-B Drainage Area Meets the Same Standard From Page 50, the 2-, 10- and 100-year design storm total peak flow rates from Post-B drainage area are 1.24, 2.41 and 4.74 cfs, respectively. The corresponding allowable design storm peak flow rates for 2-, 10- and 100-year design storms are 0.92, 2.27 and 4.30 cfs. Therefore, Post-B drainage area does not meet the Stormwater Runoff Quantity Requirements of N.J.A.C. 7:8-5.6(b)3. ## Step 6: Determine Whether the Post-B Drainage Area Meets the Stormwater Runoff Quantity Standards of N.J.A.C. 7:8-5.6(b)1 As demonstrated above, the Post-B drainage area does not meet the Stormwater Runoff Quantity Control Requirements of N.J.A.C. 7:8-5.6(b)3. A comparison of the pre- and post-construction design storm peak flow rates is made to determine whether Post-B drainage area meets the Stormwater Runoff Quantity Control Requirements of N.J.A.C. 7:8-5.6(b)1. | Drainage Area Name | Pre-construction Design Storm Flow Rate (cfs) | | | Post-construction Design Storm Flow Rate (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | 2-year | 10-year | 100-year | | Post-B1 (building or walkway) | 1.76 | 2.81 | 4.80 | 0.57 | 0.90 | 1.54 | | Post-B2 (open space/grass > 75% and woods) | 0.17 | 0.45 | 1.07 | 0.90 | 1.91 | 3.93 | | Total Post-B (Hydrograph addition) | 1.83 | 3.03 | 5.37 | 1.24 | 2.41 | 4.74 | The comparisons between the pre- and post-construction design storm peak flow rates show that the peak flow rates of the post-construction condition are less than the peak flow rates of the pre-construction. However, N.J.A.C. 7:8-5.6(b)1 does not require a comparison of the pre- and post-construction condition peak flow rates. This standard requires the demonstration that the post-construction runoff hydrographs for the 2-, 10- and 100-year design storm events do not exceed, at any point in time, the pre-construction runoff hydrographs for the same storm events. Therefore, from the definition of a hydrograph on Page 2, this standard means that the flow rates of the post-construction hydrograph at every point in time must be less than the flow rates of the pre-construction hydrograph for the same instance of time. A comparison of the 100-year design storm hydrographs for the pre-construction and post-construction conditions for the Post-B drainage area is shown below.

32. Table 32

BMP 2026, Ch 5, p. 63

Time (hours) Pre-construction flow (cfs) Post-construction flow (cfs) Difference (Post-Pre) (cfs) Time (hours) Pre-construction flow (cfs) Post-construction flow (cfs) Difference (Post-Pre) (cfs)
12.00 4.57 2.79 -1.78 12.55 1.19 1.13 -0.06
12.05 5.44 3.94 -1.5 12.60 1.07 1.04 -0.03
12.10 4.35 4.78 0.43 12.65 0.97 0.93 -0.04
12.15 3.28 4.54 1.26 12.70 0.88 0.87 -0.01
12.20 3.02 4.12 1.10 12.75 0.8 0.82 0.02
12.25 2.87 3.06 0.19 12.80 0.74 0.78 0.04
12.30 2.63 2.39 -0.24 12.85 0.68 0.74 0.06
12.35 2.34 1.89 -0.45 12.90 0.64 0.71 0.07
12.40 2.03 1.6 -0.43 12.95 0.6 0.68 0.08
12.45 1.73 1.38 -0.35 13.00 0.56 0.65 0.09
12.50 1.43 1.26 -0.17
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Time (hours) | Pre-construction flow (cfs) | Post-construction flow (cfs) | Difference (Post-Pre) (cfs) | Time (hours) | Pre-construction flow (cfs) | Post-construction flow (cfs) | Difference (Post-Pre) (cfs) | | --- | --- | --- | --- | --- | --- | --- | --- | | 12.00 | 4.57 | 2.79 | -1.78 | 12.55 | 1.19 | 1.13 | -0.06 | | 12.05 | 5.44 | 3.94 | -1.5 | 12.60 | 1.07 | 1.04 | -0.03 | | 12.10 | 4.35 | 4.78 | 0.43 | 12.65 | 0.97 | 0.93 | -0.04 | | 12.15 | 3.28 | 4.54 | 1.26 | 12.70 | 0.88 | 0.87 | -0.01 | | 12.20 | 3.02 | 4.12 | 1.10 | 12.75 | 0.8 | 0.82 | 0.02 | | 12.25 | 2.87 | 3.06 | 0.19 | 12.80 | 0.74 | 0.78 | 0.04 | | 12.30 | 2.63 | 2.39 | -0.24 | 12.85 | 0.68 | 0.74 | 0.06 | | 12.35 | 2.34 | 1.89 | -0.45 | 12.90 | 0.64 | 0.71 | 0.07 | | 12.40 | 2.03 | 1.6 | -0.43 | 12.95 | 0.6 | 0.68 | 0.08 | | 12.45 | 1.73 | 1.38 | -0.35 | 13.00 | 0.56 | 0.65 | 0.09 | | 12.50 | 1.43 | 1.26 | -0.17 | | | | | Step 7: Since Post-B Drainage Area Failed to Meet the Stormwater Runoff Quantity Control Standards of N.J.A.C. 7:8-5.6(b), on its own, Determine Whether the Site as a Whole Meets the Stormwater Runoff Quantity Control Standards of N.J.A.C. 7:8-5.6(b) The question here is whether stormwater runoff from drainage areas Post-A and Post-B can be combined together to meet the Stormwater Runoff Quantity Control requirements either under N.J.A.C. 7:8-5.6(b)3 or N.J.A.C. 7:8-5.6(b)1. The table below illustrates combining post-construction flow rates from drainage areas A and B for each of the regulatory design storms. | Post-construction Drainage Area Designation | Allowable Design Storm Peak Flow Rate (cfs) under N.J.A.C. 7:8-5.6(b)3 | | | Design Storm Peak Flow Rate with a Small-Scale Infiltration Basin in Drainage Area Post-A | | | | --- | --- | --- | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | 2-year | 10-year | 100-year | | Post-A | 0.23 | 1.01 | 2.96 | 0.23 | 0.88 | 2.81 | | Post-B | 0.92 | 2.27 | 4.30 | 1.33 | 2.56 | 4.05 | | Post A and B Combined | 1.15 | 3.28 | 7.26 | 1.28 | 2.79 | 5.95 |

33. Table 33

BMP 2026, Ch 5, p. 63

Post-construction Drainage Area Designation Allowable Design Storm Peak Flow Rate (cfs) under N.J.A.C. 7:8-5.6(b)3 Design Storm Peak Flow Rate with a Small-Scale Infiltration Basin in Drainage Area Post-A
2-year 10-year 100-year 2-year 10-year 100-year
Post-A 0.23 1.01 2.96 0.23 0.88 2.81
Post-B 0.92 2.27 4.30 1.33 2.56 4.05
Post A and B Combined 1.15 3.28 7.26 1.28 2.79 5.95
Source context and notes | 12.40 | 2.03 | 1.6 | -0.43 | 12.95 | 0.6 | 0.68 | 0.08 | | 12.45 | 1.73 | 1.38 | -0.35 | 13.00 | 0.56 | 0.65 | 0.09 | | 12.50 | 1.43 | 1.26 | -0.17 | | | | | Step 7: Since Post-B Drainage Area Failed to Meet the Stormwater Runoff Quantity Control Standards of N.J.A.C. 7:8-5.6(b), on its own, Determine Whether the Site as a Whole Meets the Stormwater Runoff Quantity Control Standards of N.J.A.C. 7:8-5.6(b) The question here is whether stormwater runoff from drainage areas Post-A and Post-B can be combined together to meet the Stormwater Runoff Quantity Control requirements either under N.J.A.C. 7:8-5.6(b)3 or N.J.A.C. 7:8-5.6(b)1. The table below illustrates combining post-construction flow rates from drainage areas A and B for each of the regulatory design storms. | Post-construction Drainage Area Designation | Allowable Design Storm Peak Flow Rate (cfs) under N.J.A.C. 7:8-5.6(b)3 | | | Design Storm Peak Flow Rate with a Small-Scale Infiltration Basin in Drainage Area Post-A | | | | --- | --- | --- | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | 2-year | 10-year | 100-year | | Post-A | 0.23 | 1.01 | 2.96 | 0.23 | 0.88 | 2.81 | | Post-B | 0.92 | 2.27 | 4.30 | 1.33 | 2.56 | 4.05 | | Post A and B Combined | 1.15 | 3.28 | 7.26 | 1.28 | 2.79 | 5.95 | The combined post-construction 10- and 100-year storm peak flow rates for the whole site are 2.79 and 5.95 cfs, respectively, which are less than the allowable 10- and 100-year design storm peak flow rates, 3.28 cfs and 7.26 cfs, respectively. However, the combined post-construction 2-year peak flow rate of 1.28 cfs is greater than the allowable 2-year design storm peak flow rate of 1.15 cfs. If the hydrographs of the 2-year storm for the pre- and post-construction conditions are visually compared in a plot, it seems that the stormwater runoff quantity control requirements, when analyzing the site as a whole, for the 2-year design storm have been met under N.J.A.C. 7:8-5.6(b)1

34. Table 34

BMP 2026, Ch 5, p. 66

Inflow Area = 3,485 sf,100.00% Impervious, Inflow Depth = 8.96" for 100-Year event
Inflow = 0.77 cfs @ 12.07 hrs, Volume= 2,602 cf
Outflow = 0.17 cfs @ 12.31 hrs, Volume= 2,602 cf, Atten= 77%, Lag= 14.4 min
Discarded = 0.01 cfs @ 2.90 hrs, Volume= 967 cf
Primary = 0.17 cfs @ 12.31 hrs, Volume= 1,635 cf
Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs
Peak Elev= 1.96' @ 12.31 hrs Surf.Area= 550 sf Storage= 1,078 cf
Plug-Flow detention time= 295.7 min calculated for 2,602 cf (100% of inflow)
Center-of-Mass det. time= 295.6 min ( 1,031.8 - 736.2 )
Volume Invert Avail.Storage Storage Description
#1 0.00' 2,200 cf Custom Stage Data (Prismatic) Listed below
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet)
0.00 550 0 0
1.00 550 550 550
2.00 550 550 1,100
3.00 550 550 1,650
4.00 550 550 2,200
Device Routing Invert Outlet Devices
#1 Discarded 0.00' 0.50 in/hr Exfiltration over Surface area below 2.00'
#2 Primary 0.80' 2.5" Vert. Orifice/Grate C= 0.600
Discarded OutFlow Max=0.01 cfs @ 2.90 hrs HW=0.04' (Free Discharge)
+1=Exfiltration (Exfiltration Controls 0.01 cfs)
Primary OutFlow Max=0.17 cfs @ 12.31 hrs HW=1.96' (Free Discharge)
+2=Orifice/Grate (Orifice Controls 0.17 cfs @ 4.94 fps)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. # 100-year Design Storm Summary Report | Inflow Area = 3,485 sf,100.00% Impervious, Inflow Depth = 8.96" for 100-Year event | | | | | | --- | --- | --- | --- | --- | | Inflow = 0.77 cfs @ 12.07 hrs, Volume= 2,602 cf | | | | | | Outflow = 0.17 cfs @ 12.31 hrs, Volume= 2,602 cf, Atten= 77%, Lag= 14.4 min | | | | | | Discarded = 0.01 cfs @ 2.90 hrs, Volume= 967 cf | | | | | | Primary = 0.17 cfs @ 12.31 hrs, Volume= 1,635 cf | | | | | | Routing by Stor-Ind method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs | | | | | | Peak Elev= 1.96' @ 12.31 hrs Surf.Area= 550 sf Storage= 1,078 cf | | | | | | Plug-Flow detention time= 295.7 min calculated for 2,602 cf (100% of inflow) | | | | | | Center-of-Mass det. time= 295.6 min ( 1,031.8 - 736.2 ) | | | | | | Volume | Invert | Avail.Storage | Storage Description | | | #1 | 0.00' | 2,200 cf | Custom Stage Data (Prismatic) Listed below | | | Elevation (feet) | Surf.Area (sq-ft) | Inc.Store (cubic-feet) | Cum.Store (cubic-feet) | | | 0.00 | 550 | 0 | 0 | | | 1.00 | 550 | 550 | 550 | | | 2.00 | 550 | 550 | 1,100 | | | 3.00 | 550 | 550 | 1,650 | | | 4.00 | 550 | 550 | 2,200 | | | Device | Routing | Invert | Outlet Devices | | | #1 | Discarded | 0.00' | 0.50 in/hr Exfiltration over Surface area below 2.00' | | | #2 | Primary | 0.80' | 2.5" Vert. Orifice/Grate C= 0.600 | | | Discarded OutFlow Max=0.01 cfs @ 2.90 hrs HW=0.04' (Free Discharge) | | | | | | +1=Exfiltration (Exfiltration Controls 0.01 cfs) | | | | | | Primary OutFlow Max=0.17 cfs @ 12.31 hrs HW=1.96' (Free Discharge) | | | | | | +2=Orifice/Grate (Orifice Controls 0.17 cfs @ 4.94 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. The peak flow rates resulting from the proposed design are as follows: | Post-construction Drainage Area Designation | Allowable Design Storm Peak Flow Rate (cfs) | | | Design Storm Peak Flow Rates with two Small-Scale Bioretention Basin (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | 2-year | 10-year | 100-year | | Post-B1 (building/walkway) after two small-scale bioretention basins | 0.88 | 2.11 | 3.84 | 0.02 | 0.18 | 0.34 | | Post-B2 (open space, grass > 75% and woods) | 0.09 | 0.34 | 0.86 | 0.90 | 1.91 | 3.93 | | Post-B | 0.97 | 2.45 | 4.70 | 0.90 | 2.08 | 4.26 |

35. Table 35

BMP 2026, Ch 5, p. 66

Post-construction Drainage Area Designation Allowable Design Storm Peak Flow Rate (cfs) Design Storm Peak Flow Rates with two Small-Scale Bioretention Basin (cfs)
2-year 10-year 100-year 2-year 10-year 100-year
Post-B1 (building/walkway) after two small-scale bioretention basins 0.88 2.11 3.84 0.02 0.18 0.34
Post-B2 (open space, grass > 75% and woods) 0.09 0.34 0.86 0.90 1.91 3.93
Post-B 0.97 2.45 4.70 0.90 2.08 4.26
Source context and notes | +1=Exfiltration (Exfiltration Controls 0.01 cfs) | | | | | | Primary OutFlow Max=0.17 cfs @ 12.31 hrs HW=1.96' (Free Discharge) | | | | | | +2=Orifice/Grate (Orifice Controls 0.17 cfs @ 4.94 fps) | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. The peak flow rates resulting from the proposed design are as follows: | Post-construction Drainage Area Designation | Allowable Design Storm Peak Flow Rate (cfs) | | | Design Storm Peak Flow Rates with two Small-Scale Bioretention Basin (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | 2-year | 10-year | 100-year | | Post-B1 (building/walkway) after two small-scale bioretention basins | 0.88 | 2.11 | 3.84 | 0.02 | 0.18 | 0.34 | | Post-B2 (open space, grass > 75% and woods) | 0.09 | 0.34 | 0.86 | 0.90 | 1.91 | 3.93 | | Post-B | 0.97 | 2.45 | 4.70 | 0.90 | 2.08 | 4.26 |

36. Table 36

BMP 2026, Ch 5, p. 69

Inflow Area = 32,670 sf, 21.33% Impervious, Inflow Depth = 7.13" for 100-Year event
Inflow = 4.74 cfs @ 12.12 hrs, Volume= 19,411.7 cf
Outflow = 3.95 cfs @ 12.34 hrs, Volume= 19,411.7 cf, Atten= 17%, Lag= 13.6 min
Routing by Stor-Ind+Trans method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs
Max. Velocity= 1.31 fps, Min. Travel Time= 8.3 min
Avg. Velocity = 0.26 fps, Avg. Travel Time= 40.9 min
Peak Storage= 1,980.0 cf @ 12.20 hrs
Average Depth at Peak Storage= 0.40'
Bank-Full Depth= 0.50' Flow Area= 4.0 sf, Capacity= 5.94 cfs
6.00' x 0.50' deep channel, n= 0.030 Earth, grassed & winding
Side Slope Z-value= 4.0' Top Width= 10.00'
Length= 650.00' Slope= 0.0031'
Inlet Invert= 2.000', Outlet Invert= -0.015'
Source context and notes # Step 1: Design the Grass Swale Grass swales are one of the green infrastructure BMPs listed in Table 5-1 of N.J.A.C. 7:8-5.2, but as stated in this table, they cannot be used to meet the groundwater recharge or stormwater runoff quantity requirements of N.J.A.C. 7:8-5.4 and 5.6. However, grass swales can be designed to provide conveyance of stormwater runoff from one drainage area to another drainage area. A grass swale also can be designed to convey flows at a lower flow velocity, which results in a slower time of concentration, than that of a stormwater drainage pipe, which typically has a smooth surface. Assuming the grass swale has a bottom width of 6 ft, a depth of 0.5 ft, a slope of 0.46%, a length of 650 ft and a Manning's roughness coefficient 0.03, the grass swale will be able to convey the peak flow of stormwater runoff produced by the 100-year design storm with a runoff depth of 0.36 ft and a maximum flow velocity of 1.51 fps, which is under the maximum allowable velocity of 2.5 fps, for sandy clay loam soil texture as suggested in the Standards for Soil Erosion and Sediment Control in New Jersey. ## Grass Swale Summary Report for the 100-year Design Storm | Inflow Area = | 32,670 sf, 21.33% Impervious, Inflow Depth = 7.13" for 100-Year event | | --- | --- | | Inflow = | 4.74 cfs @ 12.12 hrs, Volume= 19,411.7 cf | | Outflow = | 3.95 cfs @ 12.34 hrs, Volume= 19,411.7 cf, Atten= 17%, Lag= 13.6 min | | Routing by Stor-Ind+Trans method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs | | | Max. Velocity= 1.31 fps, Min. Travel Time= 8.3 min | | | Avg. Velocity = 0.26 fps, Avg. Travel Time= 40.9 min | | | Peak Storage= 1,980.0 cf @ 12.20 hrs | | | Average Depth at Peak Storage= 0.40' | | | Bank-Full Depth= 0.50' Flow Area= 4.0 sf, Capacity= 5.94 cfs | | | 6.00' x 0.50' deep channel, n= 0.030 Earth, grassed & winding | | | Side Slope Z-value= 4.0' Top Width= 10.00' | | | Length= 650.00' Slope= 0.0031' | | | Inlet Invert= 2.000', Outlet Invert= -0.015' | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission.

37. Table 37

BMP 2026, Ch 5, p. 70

Inflow Area = 32,670 sf, 21.33% Impervious, Inflow Depth = 3.58" for 10-Year event
Inflow = 2.41 cfs @ 12.11 hrs, Volume= 9,742.6 cf
Outflow = 1.89 cfs @ 12.39 hrs, Volume= 9,742.5 cf, Atten= 22%, Lag= 16.9 min
Routing by Stor-Ind+Trans method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs
Max. Velocity= 1.03 fps, Min. Travel Time= 10.6 min
Avg. Velocity = 0.21 fps, Avg. Travel Time= 51.4 min
Peak Storage= 1,208.8 cf @ 12.22 hrs
Average Depth at Peak Storage= 0.26'
Bank-Full Depth= 0.50' Flow Area= 4.0 sf, Capacity= 5.94 cfs
6.00' x 0.50' deep channel, n= 0.030 Earth, grassed & winding
Side Slope Z-value= 4.0 ? Top Width= 10.00'
Length= 650.00' Slope= 0.0031 ?
Inlet Invert= 2.000', Outlet Invert= -0.015'
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. # Grass Swale Summary Report for the 10-year Design Storm | Inflow Area = | 32,670 sf, 21.33% Impervious, Inflow Depth = 3.58" for 10-Year event | | --- | --- | | Inflow = | 2.41 cfs @ 12.11 hrs, Volume= 9,742.6 cf | | Outflow = | 1.89 cfs @ 12.39 hrs, Volume= 9,742.5 cf, Atten= 22%, Lag= 16.9 min | | Routing by Stor-Ind+Trans method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs | | | Max. Velocity= 1.03 fps, Min. Travel Time= 10.6 min | | | Avg. Velocity = 0.21 fps, Avg. Travel Time= 51.4 min | | | Peak Storage= 1,208.8 cf @ 12.22 hrs | | | Average Depth at Peak Storage= 0.26' | | | Bank-Full Depth= 0.50' Flow Area= 4.0 sf, Capacity= 5.94 cfs | | | 6.00' x 0.50' deep channel, n= 0.030 Earth, grassed & winding | | | Side Slope Z-value= 4.0 ? Top Width= 10.00' | | | Length= 650.00' Slope= 0.0031 ? | | | Inlet Invert= 2.000', Outlet Invert= -0.015' | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. # Grass Swale Summary Report for the 2-year Design Storm | Inflow Area = | 32,670 sf, 21.33% Impervious, Inflow Depth = 1.85" for 2-Year event | | --- | --- | | Inflow = | 1.24 cfs @ 12.11 hrs, Volume= 5,027.6 cf | | Outflow = | 0.89 cfs @ 12.46 hrs, Volume= 5,027.6 cf, Atten= 28%, Lag= 21.3 min | | Routing by Stor-Ind+Trans method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs | | | Max. Velocity= 0.79 fps, Min. Travel Time= 13.7 min | | | Avg. Velocity = 0.17 fps, Avg. Travel Time= 62.8 min | | | Peak Storage= 738.6 cf @ 12.23 hrs | | | Average Depth at Peak Storage= 0.17' | | | Bank-Full Depth= 0.50' Flow Area= 4.0 sf, Capacity= 5.94 cfs | | | 6.00' x 0.50' deep channel, n= 0.030 Earth, grassed & winding | | | Side Slope Z-value= 4.0 ? Top Width= 10.00' | | | Length= 650.00' Slope= 0.0031 ? | | | Inlet Invert= 2.000', Outlet Invert= -0.015' | |

38. Table 38

BMP 2026, Ch 5, p. 70

Inflow Area = 32,670 sf, 21.33% Impervious, Inflow Depth = 1.85" for 2-Year event
Inflow = 1.24 cfs @ 12.11 hrs, Volume= 5,027.6 cf
Outflow = 0.89 cfs @ 12.46 hrs, Volume= 5,027.6 cf, Atten= 28%, Lag= 21.3 min
Routing by Stor-Ind+Trans method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs
Max. Velocity= 0.79 fps, Min. Travel Time= 13.7 min
Avg. Velocity = 0.17 fps, Avg. Travel Time= 62.8 min
Peak Storage= 738.6 cf @ 12.23 hrs
Average Depth at Peak Storage= 0.17'
Bank-Full Depth= 0.50' Flow Area= 4.0 sf, Capacity= 5.94 cfs
6.00' x 0.50' deep channel, n= 0.030 Earth, grassed & winding
Side Slope Z-value= 4.0 ? Top Width= 10.00'
Length= 650.00' Slope= 0.0031 ?
Inlet Invert= 2.000', Outlet Invert= -0.015'
Source context and notes | Side Slope Z-value= 4.0 ? Top Width= 10.00' | | | Length= 650.00' Slope= 0.0031 ? | | | Inlet Invert= 2.000', Outlet Invert= -0.015' | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. # Grass Swale Summary Report for the 2-year Design Storm | Inflow Area = | 32,670 sf, 21.33% Impervious, Inflow Depth = 1.85" for 2-Year event | | --- | --- | | Inflow = | 1.24 cfs @ 12.11 hrs, Volume= 5,027.6 cf | | Outflow = | 0.89 cfs @ 12.46 hrs, Volume= 5,027.6 cf, Atten= 28%, Lag= 21.3 min | | Routing by Stor-Ind+Trans method, Time Span= 0.00-48.00 hrs, dt= 0.05 hrs | | | Max. Velocity= 0.79 fps, Min. Travel Time= 13.7 min | | | Avg. Velocity = 0.17 fps, Avg. Travel Time= 62.8 min | | | Peak Storage= 738.6 cf @ 12.23 hrs | | | Average Depth at Peak Storage= 0.17' | | | Bank-Full Depth= 0.50' Flow Area= 4.0 sf, Capacity= 5.94 cfs | | | 6.00' x 0.50' deep channel, n= 0.030 Earth, grassed & winding | | | Side Slope Z-value= 4.0 ? Top Width= 10.00' | | | Length= 650.00' Slope= 0.0031 ? | | | Inlet Invert= 2.000', Outlet Invert= -0.015' | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. To summarize the reports listed above, the stormwater runoff peak flow rates for the 2-, 10- and 100-year design storms, generated by the Post-B drainage area and conveyed by the grass swale to the discharge point of convergence in Post-A drainage area are listed in the table below. | Post-construction Drainage Area | Design Storm Peak Flow Rates with a Grass Swale (cfs) | | | | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | | Post-B | 0.89 | 1.89 | 3.95 |

39. Table 39

BMP 2026, Ch 5, p. 70

Post-construction Drainage Area Design Storm Peak Flow Rates with a Grass Swale (cfs)
2-year 10-year 100-year
Post-B 0.89 1.89 3.95
Source context and notes | Side Slope Z-value= 4.0 ? Top Width= 10.00' | | | Length= 650.00' Slope= 0.0031 ? | | | Inlet Invert= 2.000', Outlet Invert= -0.015' | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. To summarize the reports listed above, the stormwater runoff peak flow rates for the 2-, 10- and 100-year design storms, generated by the Post-B drainage area and conveyed by the grass swale to the discharge point of convergence in Post-A drainage area are listed in the table below. | Post-construction Drainage Area | Design Storm Peak Flow Rates with a Grass Swale (cfs) | | | | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | | Post-B | 0.89 | 1.89 | 3.95 |

40. Table 40

BMP 2026, Ch 5, p. 71

Post-construction Drainage Area Designation Allowable Design Storm Peak Flow Rate (cfs) per the N.J.A.C. 7:8-5.6(b)3 Standard Design Storm Peak Flow Rate (cfs)
2-year 10-year 100-year 2-year 10-year 100-year
Post-A 0.23 1.01 2.96 0.23 0.87 2.80
Post-B 0.92 2.27 4.30 0.89 1.89 3.95
Post A and B Combined 1.15 3.28 7.26 1.12 2.76 6.75
Source context and notes Source revision: January 2026. Step 2: Address Stormwater Runoff Quantity Control Although not mentioned in the initial description, the stormwater runoff generated by the proposed building and walkway will flow as overland flow across the proposed lawn area. The lawn area is graded to direct this runoff to the same grass swale and discharge point for the Post-A drainage area. The stormwater runoff generated by both the roof and the non-vehicular walkway do not require water quality treatment. Drainage area Post-A1 will still require a small-scale infiltration basin to provide the required stormwater runoff quantity and quality controls, in addition to the groundwater recharge requirement for the stormwater runoff generated by the proposed gravel parking lot. Drainage area Post-A2 will not be disturbed and is therefore not subject to the stormwater runoff quality and quantity requirements, nor those for groundwater recharge. In this example, the initial description states that the stormwater runoff from Drainage Areas A and B converge into one discharge point (i.e., the point of analysis A) before leaving the site. Therefore, the peak flow rates for 2-, 10- and 100-year design storms of the two drainage areas can be added to calculate the peak flow rates at the discharge location. | Post-construction Drainage Area Designation | Allowable Design Storm Peak Flow Rate (cfs) per the N.J.A.C. 7:8-5.6(b)3 Standard | | | Design Storm Peak Flow Rate (cfs) | | | | --- | --- | --- | --- | --- | --- | --- | | | 2-year | 10-year | 100-year | 2-year | 10-year | 100-year | | Post-A | 0.23 | 1.01 | 2.96 | 0.23 | 0.87 | 2.80 | | Post-B | 0.92 | 2.27 | 4.30 | 0.89 | 1.89 | 3.95 | | Post A and B Combined | 1.15 | 3.28 | 7.26 | 1.12 | 2.76 | 6.75 | As the results show in the table above, each of the combined post-construction peak flow rates for the 2-, 10- and 100-year design storms are less than the respective allowable design storm peak flow rates. Therefore, the site as a whole meets the stormwater runoff quantity standards of N.J.A.C. 7:8-5.6(b)3. Step 3: Address Groundwater Recharge Regarding groundwater recharge, both drainage area Post-B and drainage area Pre-B contain 0.5 acres of impervious surface, meaning there is no change in impervious cover area from the pre-construction condition to the post-construction condition. However, the project also proposes to change the land cover from woods to grass lawn, which will reduce the amount of groundwater recharge provided. Therefore, an evaluation of the groundwater recharge deficit is needed. See Chapter 6 of this manual for guidance on performing a groundwater recharge analysis.

41. Table 41

BMP 2026, Ch 5, p. 74

Frequency of Storms NOAA NWS PFDS Precipitation Depth (inches)
2-year 3.30
10-year 5.02
100-year 8.42
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Frequency of Storms | NOAA NWS PFDS Precipitation Depth (inches) | | --- | --- | | 2-year | 3.30 | | 10-year | 5.02 | | 100-year | 8.42 | ## Step 2: Calculate the Current and Projected Precipitation Depths To calculate the current and projected precipitation depths, the current precipitation adjustment factors and the future precipitation change factors must be obtained from Table 5-5 and Table 5-6, respectively, of the Stormwater Management rules. The site is in Somerset County. The current precipitation adjustment factors for the 2-, 10- and 100-year current storm events in Somerset County are 1.00, 1.03 and 1.09, respectively. The future precipitation change factors for the 2-, 10- and 100-year projected storm events in Somerset County are 1.19, 1.24 and 1.48, respectively. Multiply the current precipitation adjustment factor with the precipitation depths obtained in Step 1 to obtain the current precipitation depths. Multiply the future precipitation change factors with the precipitation depths obtained in Step 1 to obtain the projected precipitation depths for the design storms. The current and projected precipitation depths for each storm frequency are listed in the table below.

42. Table 42

BMP 2026, Ch 5, p. 74

Design Storms NOAA NWS PFDS Precipitation Depth (inches) Current Precipitation Depths (inches) Future Projected Precipitation Depths (inches)
2-year 3.30 3.30 3.93
10-year 5.02 5.17 6.22
100-year 8.42 9.18 12.46
Source context and notes | 100-year | 8.42 | ## Step 2: Calculate the Current and Projected Precipitation Depths To calculate the current and projected precipitation depths, the current precipitation adjustment factors and the future precipitation change factors must be obtained from Table 5-5 and Table 5-6, respectively, of the Stormwater Management rules. The site is in Somerset County. The current precipitation adjustment factors for the 2-, 10- and 100-year current storm events in Somerset County are 1.00, 1.03 and 1.09, respectively. The future precipitation change factors for the 2-, 10- and 100-year projected storm events in Somerset County are 1.19, 1.24 and 1.48, respectively. Multiply the current precipitation adjustment factor with the precipitation depths obtained in Step 1 to obtain the current precipitation depths. Multiply the future precipitation change factors with the precipitation depths obtained in Step 1 to obtain the projected precipitation depths for the design storms. The current and projected precipitation depths for each storm frequency are listed in the table below. | Design Storms | NOAA NWS PFDS Precipitation Depth (inches) | Current Precipitation Depths (inches) | Future Projected Precipitation Depths (inches) | | --- | --- | --- | --- | | 2-year | 3.30 | 3.30 | 3.93 | | 10-year | 5.02 | 5.17 | 6.22 | | 100-year | 8.42 | 9.18 | 12.46 | ## Step 3: Design the SSGI Bioretention Basins for the Water Quality Design Standard The Water Quality Design Storm (WQDS) is 1.25 inches of precipitation in two hours. The runoff volume of the WQDS calculated by using the NRCS Methodology is 1,878 cf. Two SSGI bioretention BMPs are designed to treat the WQDS runoff from the proposed parking lot. Each proposed SSGI bioretention BMP will receive and treat 938.9 cf of total WQDS runoff. Each SSGI bioretention BMP is designed to have a footprint of 950 sf and a depth of 2 ft. Although the ground elevations may vary at different locations of a project site, for the sake of simplicity in illustrating this design example, the proposed ground elevations of the two proposed SSGI bioretention BMPs are both assumed to be at EL. 102.00 ft. The bottoms of the proposed SSGI bioretention BMPs are both assumed to be at EL. 100.00 ft.

43. Table 43

BMP 2026, Ch 5, p. 75

Ex_5-8 NoExfiltration NJ DEP 2-hr WQL Rainfall=1.25° Prepared by NJDEP Printed 7/12/2023 HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC Page 139
Summary for Pond 34P: SS Bioretention S
Inflow Area = 10,890 sf,100.00% Impervious, Inflow Depth = 1.03" for WQL event
Inflow = 0.77 cfs @ 1.08 hrs, Volume= 938.9 cf
Outflow = 0.00 cfs @ 0.00 hrs, Volume= 0.0 cf, Atten= 100%, Lag= 0.0 min
Primary = 0.00 cfs @ 0.00 hrs, Volume= 0.0 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 100.988' @ 2.09 hrs Surf.Area= 950 sf Storage= 938.9 cf
Plug-Flow detention time= (not calculated: initial storage exceeds outflow)
Center-of-Mass det. time= (not calculated: no outflow)
Volume Invert Avail.Storage Storage Description
#1 100.000' 1,900.0 cf Custom Stage Data (Conic) Listed below (Recalc)
Elevation Surf.Area Inc.Store Cumb.-feet Cum.Store Wet.Area (feet) (sq-ft) (cubic-feet) (sq-ft)
100.000 950 0.0 0.0 950
101.000 950 950.0 950.0 1,059
102.000 950 950.0 1,900.0 1,169
Device Routing Invert Outlet Devices
#1 Device 2 100.990' 24.0" W x 12.0" H Vert. Orifice/Grate C= 0.600
#2 Primary 100.000' 12.0" Round Culvert L= 150.00' CPP, projecting, no headwall, Ke= 0.900 Inlet / Outlet Invert= 100.000' / 98.500' S= 0.0100' /' C= 0.900 n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf
Primary OutFlow Max=0.00 cfs @ 0.00 hrs HW=100.000' TW=95.500' (Dynamic Tailwater) 2=Culvert ( Controls 0.00 cfs) 1=Orifice/Grate ( Controls 0.00 cfs)
Source context and notes Source revision: January 2026. The proposed outlet structure has a 24-inch by 12-inch opening as the orifice with a 12-inch pipe located down-gradient of the orifice to convey the runoff from storms larger than the WQDS to the down-gradient SSGI infiltration BMPs. The invert of the 24-inch by 12-inch orifice shall be set at 0.99 ft above the BMP bottom to provide a storage and infiltration volume of 938.9 cf. The WQDS routing calculation for the proposed SSGI bioretention BMP is depicted below. Exfiltration is not used in the routing. Take note that the design of the outlet control structures and the configuration of the BMPs are just one example of the many possible variations that an engineer may incorporate into the design. WQDS Routing Summary Report | Ex_5-8 NoExfiltration NJ DEP 2-hr WQL Rainfall=1.25° Prepared by NJDEP Printed 7/12/2023 HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC Page 139 | | | | | | | --- | --- | --- | --- | --- | --- | | Summary for Pond 34P: SS Bioretention S | | | | | | | Inflow Area = 10,890 sf,100.00% Impervious, Inflow Depth = 1.03" for WQL event | | | | | | | Inflow = 0.77 cfs @ 1.08 hrs, Volume= 938.9 cf | | | | | | | Outflow = 0.00 cfs @ 0.00 hrs, Volume= 0.0 cf, Atten= 100%, Lag= 0.0 min | | | | | | | Primary = 0.00 cfs @ 0.00 hrs, Volume= 0.0 cf | | | | | | | Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs | | | | | | | Peak Elev= 100.988' @ 2.09 hrs Surf.Area= 950 sf Storage= 938.9 cf | | | | | | | Plug-Flow detention time= (not calculated: initial storage exceeds outflow) | | | | | | | Center-of-Mass det. time= (not calculated: no outflow) | | | | | | | Volume Invert Avail.Storage Storage Description | | | | | | | #1 100.000' 1,900.0 cf Custom Stage Data (Conic) Listed below (Recalc) | | | | | | | Elevation Surf.Area Inc.Store Cumb.-feet Cum.Store Wet.Area (feet) (sq-ft) (cubic-feet) (sq-ft) | | | | | | | 100.000 950 0.0 0.0 950 | | | | | | | 101.000 950 950.0 950.0 1,059 | | | | | | | 102.000 950 950.0 1,900.0 1,169 | | | | | | | Device Routing Invert Outlet Devices | | | | | | | #1 Device 2 100.990' 24.0" W x 12.0" H Vert. Orifice/Grate C= 0.600 | | | | | | | #2 Primary 100.000' 12.0" Round Culvert L= 150.00' CPP, projecting, no headwall, Ke= 0.900 Inlet / Outlet Invert= 100.000' / 98.500' S= 0.0100' /' C= 0.900 n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf | | | | | | | Primary OutFlow Max=0.00 cfs @ 0.00 hrs HW=100.000' TW=95.500' (Dynamic Tailwater) 2=Culvert ( Controls 0.00 cfs) 1=Orifice/Grate ( Controls 0.00 cfs) | | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. Routing for the projected 100-year storm is also an essential calculation which will ascertain whether the proposed BMP will not be overtopped during the projected 100-year storm. The result shows that the outlet structure of each of the proposed SSGI bioretention BMPs has sufficient capacity to pass runoff flow to its down-gradient SSGI infiltration BMP without being overtopped during the projected 100-year storm which addresses the impacts of climate change.

44. Table 44

BMP 2026, Ch 5, p. 76

Ex_5-8 NoExfiltration NOAA 24-hr C Proj_100yr Rainfall=12.46"
Prepared by NJDEP Printed 7/12/2023
HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC Page 79
Summary for Pond 34P: SS Bioretention S
Inflow Area = 10,890 sf,100.00% Impervious, Inflow Depth = 12.22" for Proj_100yr event
Inflow = 3.66 cfs @ 12.09 hrs, Volume= 11,088.2 cf
Outflow = 3.25 cfs @ 12.11 hrs, Volume= 10,147.7 cf, Atten= 11%, Lag= 1.2 min
Primary = 3.25 cfs @ 12.11 hrs, Volume= 10,147.7 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 101.687' @ 12.11 hrs Surf.Area= 950 sf Storage= 1,602.7 cf
Plug-Flow detention time= 97.2 min calculated for 10,144.8 cf (91% of inflow)
Center-of-Mass det. time= 50.3 min (783.0 - 732.6)
Volume Invert Avail.Storage Storage Description
#1 100.000' 1,900.0 cf Custom Stage Data (Conic) Listed below (Recalc)
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet) Wet.Area (sq-ft)
100.000 950 0.0 0.0 950
101.000 950 950.0 950.0 1,059
102.000 950 950.0 1,900.0 1,169
Device Routing Invert Outlet Devices
#1 Device 2 100.990' 24.0" W x 12.0" H Vert. Orifice/Grate C= 0.600
#2 Primary 100.000' 12.0" Round Culvert
L= 150.00' CPP, projecting, no headwall, Ke= 0.900
Inlet / Outlet Invert= 100.000' / 98.500' S= 0.0100' /' Cc= 0.900
n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf
Primary OutFlow Max=3.25 cfs @ 12.11 hrs HW=101.687' TW=98.885' (Dynamic Tailwater)
2=Culvert (Inlet Controls 3.25 cfs @ 4.14 fps)
1=Orifice/Grate (Passes 3.25 cfs of 3.74 cfs potential flow)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Ex_5-8 NoExfiltration | | | | NOAA 24-hr C Proj_100yr Rainfall=12.46" | | | --- | --- | --- | --- | --- | --- | | Prepared by NJDEP | | | | Printed 7/12/2023 | | | HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC | | | | Page 79 | | | Summary for Pond 34P: SS Bioretention S | | | | | | | Inflow Area = 10,890 sf,100.00% Impervious, Inflow Depth = 12.22" for Proj_100yr event | | | | | | | Inflow = 3.66 cfs @ 12.09 hrs, Volume= 11,088.2 cf | | | | | | | Outflow = 3.25 cfs @ 12.11 hrs, Volume= 10,147.7 cf, Atten= 11%, Lag= 1.2 min | | | | | | | Primary = 3.25 cfs @ 12.11 hrs, Volume= 10,147.7 cf | | | | | | | Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs | | | | | | | Peak Elev= 101.687' @ 12.11 hrs Surf.Area= 950 sf Storage= 1,602.7 cf | | | | | | | Plug-Flow detention time= 97.2 min calculated for 10,144.8 cf (91% of inflow) | | | | | | | Center-of-Mass det. time= 50.3 min (783.0 - 732.6) | | | | | | | Volume | Invert | Avail.Storage | Storage Description | | | | #1 | 100.000' | 1,900.0 cf | Custom Stage Data (Conic) Listed below (Recalc) | | | | Elevation (feet) | Surf.Area (sq-ft) | Inc.Store (cubic-feet) | Cum.Store (cubic-feet) | Wet.Area (sq-ft) | | | 100.000 | 950 | 0.0 | 0.0 | 950 | | | 101.000 | 950 | 950.0 | 950.0 | 1,059 | | | 102.000 | 950 | 950.0 | 1,900.0 | 1,169 | | | Device | Routing | Invert | Outlet Devices | | | | #1 | Device 2 | 100.990' | 24.0" W x 12.0" H Vert. Orifice/Grate C= 0.600 | | | | #2 | Primary | 100.000' | 12.0" Round Culvert | | | | | | | L= 150.00' CPP, projecting, no headwall, Ke= 0.900 | | | | | | | Inlet / Outlet Invert= 100.000' / 98.500' S= 0.0100' /' Cc= 0.900 | | | | | | | n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf | | | | Primary OutFlow Max=3.25 cfs @ 12.11 hrs HW=101.687' TW=98.885' (Dynamic Tailwater) | | | | | | | 2=Culvert (Inlet Controls 3.25 cfs @ 4.14 fps) | | | | | | | 1=Orifice/Grate (Passes 3.25 cfs of 3.74 cfs potential flow) | | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. # Step 4: Calculate the Peak Flow Rates Allowed under the Stormwater Runoff Quantity Control Standards In accordance with the 3rd option under N.J.A.C. 7:8-5.6(b), the proposed design must demonstrate that the post-construction peak runoff rates for the current and projected 2-, 10- and 100-year storm events, respectively, are 50, 75, and 80 percent, respectively, of the pre-construction peak runoff rates. Therefore, we must calculate the runoff volume and peak flow rate for the pre-construction condition in accordance with the land cover, soil type, and precipitation depths identified in Step 2, if choosing this option.

45. Table 45

BMP 2026, Ch 5, p. 77

Pre-construction Condition
Design Storm Current Precipitation Peak Flow Rate (cfs) Projected Precipitation Peak Flow Rate (cfs)
To be disturbed Undisturbed To be disturbed Undisturbed
2-year 0.19 0.05 0.49 0.12
10-year 1.40 0.35 2.35 0.59
100-year 5.61 1.40 9.75 2.44
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Pre-construction Condition | | | | | | --- | --- | --- | --- | --- | | Design Storm | Current Precipitation Peak Flow Rate (cfs) | | Projected Precipitation Peak Flow Rate (cfs) | | | | To be disturbed | Undisturbed | To be disturbed | Undisturbed | | 2-year | 0.19 | 0.05 | 0.49 | 0.12 | | 10-year | 1.40 | 0.35 | 2.35 | 0.59 | | 100-year | 5.61 | 1.40 | 9.75 | 2.44 | The peak rate reductions required, as stated above, are applied to the peak flow rates calculated for the disturbed areas, with the results shown below in the column "Post-Construction Target." These values are summed with the peak flow rate for the undisturbed area to calculate the total allowable peak flow rate for each of the current and projected design storms. | Post-Construction Condition | | | | | | | | --- | --- | --- | --- | --- | --- | --- | | Design Storm | Current Precipitation Peak Flow Rate (cfs) | | | Projected Precipitation Peak Flow Rate (cfs) | | | | | Post-Construction Target | Undisturbed | Total Allowable | Post-Construction Target | Undisturbed | Total Allowable | | 2-year | 0.10 | 0.05 | 0.15 | 0.24 | 0.12 | 0.36 | | 10-year | 1.05 | 0.35 | 1.40 | 1.76 | 0.59 | 2.35 | | 100-year | 4.49 | 1.40 | 5.89 | 7.80 | 2.44 | 10.24 | # Step 5: Design the SSGI Infiltration Basins to meet the Quantity Control Standard

46. Table 46

BMP 2026, Ch 5, p. 77

Post-Construction Condition
Design Storm Current Precipitation Peak Flow Rate (cfs) Projected Precipitation Peak Flow Rate (cfs)
Post-Construction Target Undisturbed Total Allowable Post-Construction Target Undisturbed Total Allowable
2-year 0.10 0.05 0.15 0.24 0.12 0.36
10-year 1.05 0.35 1.40 1.76 0.59 2.35
100-year 4.49 1.40 5.89 7.80 2.44 10.24
Source context and notes | Design Storm | Current Precipitation Peak Flow Rate (cfs) | | Projected Precipitation Peak Flow Rate (cfs) | | | | To be disturbed | Undisturbed | To be disturbed | Undisturbed | | 2-year | 0.19 | 0.05 | 0.49 | 0.12 | | 10-year | 1.40 | 0.35 | 2.35 | 0.59 | | 100-year | 5.61 | 1.40 | 9.75 | 2.44 | The peak rate reductions required, as stated above, are applied to the peak flow rates calculated for the disturbed areas, with the results shown below in the column "Post-Construction Target." These values are summed with the peak flow rate for the undisturbed area to calculate the total allowable peak flow rate for each of the current and projected design storms. | Post-Construction Condition | | | | | | | | --- | --- | --- | --- | --- | --- | --- | | Design Storm | Current Precipitation Peak Flow Rate (cfs) | | | Projected Precipitation Peak Flow Rate (cfs) | | | | | Post-Construction Target | Undisturbed | Total Allowable | Post-Construction Target | Undisturbed | Total Allowable | | 2-year | 0.10 | 0.05 | 0.15 | 0.24 | 0.12 | 0.36 | | 10-year | 1.05 | 0.35 | 1.40 | 1.76 | 0.59 | 2.35 | | 100-year | 4.49 | 1.40 | 5.89 | 7.80 | 2.44 | 10.24 | # Step 5: Design the SSGI Infiltration Basins to meet the Quantity Control Standard To meet the allowable peak runoff rates calculated in Step 4, two identical SSGI infiltration basins are designed to collect the clean roof runoff from the proposed building, the parking lot runoff that has been treated by the proposed SSGI bioretention BMPs and the runoff from the lawn areas. Each of the proposed two SSGI infiltration BMPs is designed with a 5,020 sf footprint and depth of 4.5 ft, meaning the top of the basin bottom surface is set at El. 95.50. The outlet structure of each proposed BMP consists of a 6-inch orifice, a 12-inch by 6-inch orifice, a 5 ft by 5 ft top broad-crested weir and a 12-inch culvert discharge pipe. Take note that the 6-inch orifice is set at EL. 97.10, or 1.60 ft above the bottom of the BMP to accommodate storage volume for the runoff that will provide groundwater recharge; recharge is discussed in Step 6. Routing calculations for both of the current and projected 100-year storms follow below.

47. Table 47

BMP 2026, Ch 5, p. 78

Ex_5-8 NoExfiltration NOAA 24-hr C Adj_100_yr Rainfall=9.18"
Prepared by NJDEP Printed 7/12/2023
HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC Page 21
Summary for Pond 37P: SS Infiltration S
Inflow Area = 43,560 sf, 75.00% Impervious, Inflow Depth = 7.54" for Adj_100_yr event
Inflow = 8.93 cfs @ 12.10 hrs, Volume= 27,360.8 cf
Outflow = 2.21 cfs @ 12.35 hrs, Volume= 19,168.6 cf, Atten= 75%, Lag= 15.0 min
Primary = 2.21 cfs @ 12.35 hrs, Volume= 19,168.6 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 98.430' @ 12.35 hrs Surf.Area= 5,020 sf Storage= 14,710.2 cf
Plug-Flow detention time= 260.7 min calculated for 19,163.3 cf (70% of inflow)
Center-of-Mass det. time= 162.6 min ( 930.1 - 767.5 )
Volume Invert Avail.Storage Storage Description
#1 95.500' 22,590.0 cf Custom Stage Data (Conic) Listed below (Recalc)
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Wet.Area (sq-ft)
95.500 5,020 0.0 0.0 5,020
96.500 5,020 5,020.0 5,020.0 5,271
97.100 5,020 3,012.0 8,032.0 5,422
97.500 5,020 2,008.0 10,040.0 5,522
98.500 5,020 5,020.0 15,060.0 5,773
99.500 5,020 5,020.0 20,080.0 6,025
100.000 5,020 2,510.0 22,590.0 6,150
Device Routing Invert Outlet Devices
#1 Device 4 99.300' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir
Head (feet) 0.200 0.400 0.600 0.800 1.000
Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Device 4 97.900' 12.0" W x 6.0" H Vert. Orifice/Grate C= 0.600
#3 Device 4 97.100' 6.0" Vert. Orifice/Grate C= 0.600
#4 Primary 95.500' 12.0" Round Culvert
L= 50.00' RCP, groove end projecting, Ke= 0.200
Inlet / Outlet Invert= 95.500' / 95.000' S= 0.0100' /' Cc= 0.900
n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf
Primary OutFlow Max=2.21 cfs @ 12.35 hrs HW=98.430' TW=94.000' (Dynamic Tailwater)
4=Culvert (Passes 2.21 cfs of 6.45 cfs potential flow)
1=Broad-Crested Rectangular Weir ( Controls 0.00 cfs)
2=Orifice/Grate (Orifice Controls 1.22 cfs @ 2.45 fps)
3=Orifice/Grate (Orifice Controls 0.98 cfs @ 5.00 fps)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Ex_5-8 NoExfiltration | | | | NOAA 24-hr C Adj_100_yr Rainfall=9.18" | | | --- | --- | --- | --- | --- | --- | | Prepared by NJDEP | | | | Printed 7/12/2023 | | | HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC | | | | Page 21 | | | Summary for Pond 37P: SS Infiltration S | | | | | | | Inflow Area = 43,560 sf, 75.00% Impervious, Inflow Depth = 7.54" for Adj_100_yr event | | | | | | | Inflow = 8.93 cfs @ 12.10 hrs, Volume= 27,360.8 cf | | | | | | | Outflow = 2.21 cfs @ 12.35 hrs, Volume= 19,168.6 cf, Atten= 75%, Lag= 15.0 min | | | | | | | Primary = 2.21 cfs @ 12.35 hrs, Volume= 19,168.6 cf | | | | | | | Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs | | | | | | | Peak Elev= 98.430' @ 12.35 hrs Surf.Area= 5,020 sf Storage= 14,710.2 cf | | | | | | | Plug-Flow detention time= 260.7 min calculated for 19,163.3 cf (70% of inflow) | | | | | | | Center-of-Mass det. time= 162.6 min ( 930.1 - 767.5 ) | | | | | | | Volume Invert Avail.Storage Storage Description | | | | | | | #1 95.500' 22,590.0 cf Custom Stage Data (Conic) Listed below (Recalc) | | | | | | | Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Wet.Area (sq-ft) | | | | | | | 95.500 | 5,020 | 0.0 | 0.0 | 5,020 | | | 96.500 | 5,020 | 5,020.0 | 5,020.0 | 5,271 | | | 97.100 | 5,020 | 3,012.0 | 8,032.0 | 5,422 | | | 97.500 | 5,020 | 2,008.0 | 10,040.0 | 5,522 | | | 98.500 | 5,020 | 5,020.0 | 15,060.0 | 5,773 | | | 99.500 | 5,020 | 5,020.0 | 20,080.0 | 6,025 | | | 100.000 | 5,020 | 2,510.0 | 22,590.0 | 6,150 | | | Device Routing Invert Outlet Devices | | | | | | | #1 Device 4 99.300' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir | | | | | | | Head (feet) 0.200 0.400 0.600 0.800 1.000 | | | | | | | Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | | | | | #2 Device 4 97.900' 12.0" W x 6.0" H Vert. Orifice/Grate C= 0.600 | | | | | | | #3 Device 4 97.100' 6.0" Vert. Orifice/Grate C= 0.600 | | | | | | | #4 Primary 95.500' 12.0" Round Culvert | | | | | | | L= 50.00' RCP, groove end projecting, Ke= 0.200 | | | | | | | Inlet / Outlet Invert= 95.500' / 95.000' S= 0.0100' /' Cc= 0.900 | | | | | | | n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf | | | | | | | Primary OutFlow Max=2.21 cfs @ 12.35 hrs HW=98.430' TW=94.000' (Dynamic Tailwater) | | | | | | | 4=Culvert (Passes 2.21 cfs of 6.45 cfs potential flow) | | | | | | | 1=Broad-Crested Rectangular Weir ( Controls 0.00 cfs) | | | | | | | 2=Orifice/Grate (Orifice Controls 1.22 cfs @ 2.45 fps) | | | | | | | 3=Orifice/Grate (Orifice Controls 0.98 cfs @ 5.00 fps) | | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission.

48. Table 48

BMP 2026, Ch 5, p. 79

Ex_5-8 NoExfiltration NOAA 24-hr C Proj_100yr Rainfall=12.46"
Prepared by NJDEP Printed 7/12/2023
HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC Page 81
Summary for Pond 37P: SS Infiltration S
Inflow Area = 43,560 sf, 75.00% Impervious, Inflow Depth = 10.68" for Proj_100yr event
Inflow = 12.23 cfs @ 12.10 hrs, Volume= 38,779.8 cf
Outflow = 3.83 cfs @ 12.31 hrs, Volume= 30,582.7 cf, Atten= 69%, Lag= 12.4 min
Primary = 3.83 cfs @ 12.31 hrs, Volume= 30,582.7 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 99.257' @ 12.31 hrs Surf.Area= 5,020 sf Storage= 18,860.1 cf
Plug-Flow detention time= 218.6 min calculated for 30,574.3 cf (79% of inflow)
Center-of-Mass det. time= 135.5 min (897.7 - 762.2)
Volume Invert Avail.Storage Storage Description
#1 95.500' 22,590.0 cf Custom Stage Data (Conic) Listed below (Recalc)
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet) Wet.Area (sq-ft)
95.500 5,020 0.0 0.0 5,020
96.500 5,020 5,020.0 5,020.0 5,271
97.100 5,020 3,012.0 8,032.0 5,422
97.500 5,020 2,008.0 10,040.0 5,522
98.500 5,020 5,020.0 15,060.0 5,773
99.500 5,020 5,020.0 20,080.0 6,025
100.000 5,020 2,510.0 22,590.0 6,150
Device Routing Invert Outlet Devices
#1 Device 4 99.300' 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir
Head (feet) 0.200 0.400 0.600 0.800 1.000
Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Device 4 97.900' 12.0" W x 6.0" H Vert. Orifice/Grate C= 0.600
#3 Device 4 97.100' 6.0" Vert. Orifice/Grate C= 0.600
#4 Primary 95.500' 12.0" Round Culvert
L= 50.00' RCP, groove end projecting, Ke= 0.200
Inlet / Outlet Invert= 95.500' / 95.000' S= 0.0100' /' C= 0.900
n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf
Primary OutFlow Max=3.83 cfs @ 12.31 hrs HW=99.257' TW=94.000' (Dynamic Tailwater)
4= Culvert (Passes 3.83 cfs of 7.46 cfs potential flow)
1= Broad-Crested Rectangular Weir (Controls 0.00 cfs)
2= Orifice/Grate (Orifice Controls 2.53 cfs @ 5.06 fps)
3= Orifice/Grate (Orifice Controls 1.31 cfs @ 6.65 fps)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Ex_5-8 NoExfiltration | | | | NOAA 24-hr C Proj_100yr Rainfall=12.46" | | | --- | --- | --- | --- | --- | --- | | Prepared by NJDEP | | | | Printed 7/12/2023 | | | HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC | | | | Page 81 | | | Summary for Pond 37P: SS Infiltration S | | | | | | | Inflow Area = | 43,560 sf, 75.00% Impervious, Inflow Depth = 10.68" for Proj_100yr event | | | | | | Inflow = | 12.23 cfs @ 12.10 hrs, Volume= 38,779.8 cf | | | | | | Outflow = | 3.83 cfs @ 12.31 hrs, Volume= 30,582.7 cf, Atten= 69%, Lag= 12.4 min | | | | | | Primary = | 3.83 cfs @ 12.31 hrs, Volume= 30,582.7 cf | | | | | | Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs | | | | | | | Peak Elev= 99.257' @ 12.31 hrs Surf.Area= 5,020 sf Storage= 18,860.1 cf | | | | | | | Plug-Flow detention time= 218.6 min calculated for 30,574.3 cf (79% of inflow) | | | | | | | Center-of-Mass det. time= 135.5 min (897.7 - 762.2) | | | | | | | Volume | Invert | Avail.Storage | Storage Description | | | | #1 | 95.500' | 22,590.0 cf | Custom Stage Data (Conic) Listed below (Recalc) | | | | Elevation (feet) | Surf.Area (sq-ft) | Inc.Store (cubic-feet) | Cum.Store (cubic-feet) | Wet.Area (sq-ft) | | | 95.500 | 5,020 | 0.0 | 0.0 | 5,020 | | | 96.500 | 5,020 | 5,020.0 | 5,020.0 | 5,271 | | | 97.100 | 5,020 | 3,012.0 | 8,032.0 | 5,422 | | | 97.500 | 5,020 | 2,008.0 | 10,040.0 | 5,522 | | | 98.500 | 5,020 | 5,020.0 | 15,060.0 | 5,773 | | | 99.500 | 5,020 | 5,020.0 | 20,080.0 | 6,025 | | | 100.000 | 5,020 | 2,510.0 | 22,590.0 | 6,150 | | | Device | Routing | Invert | Outlet Devices | | | | #1 | Device 4 | 99.300' | 20.0' long x 0.5' breadth Broad-Crested Rectangular Weir | | | | | | | Head (feet) 0.200 0.400 0.600 0.800 1.000 | | | | | | | Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | | #2 | Device 4 | 97.900' | 12.0" W x 6.0" H Vert. Orifice/Grate C= 0.600 | | | | #3 | Device 4 | 97.100' | 6.0" Vert. Orifice/Grate C= 0.600 | | | | #4 | Primary | 95.500' | 12.0" Round Culvert | | | | | | | L= 50.00' RCP, groove end projecting, Ke= 0.200 | | | | | | | Inlet / Outlet Invert= 95.500' / 95.000' S= 0.0100' /' C= 0.900 | | | | | | | n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf | | | | Primary OutFlow Max=3.83 cfs @ 12.31 hrs HW=99.257' TW=94.000' (Dynamic Tailwater) | | | | | | | 4= Culvert (Passes 3.83 cfs of 7.46 cfs potential flow) | | | | | | | 1= Broad-Crested Rectangular Weir (Controls 0.00 cfs) | | | | | | | 2= Orifice/Grate (Orifice Controls 2.53 cfs @ 5.06 fps) | | | | | | | 3= Orifice/Grate (Orifice Controls 1.31 cfs @ 6.65 fps) | | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. Take note that the configuration of outlets shown above is just one example of the many possible configurations and outlet designs. Designers and reviewers shall not interpret the design and arrangement shown in the routing calculations literally. The post-construction runoff peak rates to be discharged offsite, including the discharges from the proposed SSGI infiltration BMP and the runoff from the undisturbed woods, have been added as text to the routing diagram provided below. Note that the peak flow rate from each element, or "node," cannot be arithmetically added to calculate the total discharge from the site, i.e., Node 7L, because the time to peak for each element is different. The post construction runoff peak flow rates for the off-site discharges are also provided in the next table.

49. Table 49

BMP 2026, Ch 5, p. 80

Post-Construction Condition Off-Site Discharges
Design Storm Current Precipitation Peak Flow Rate (cfs) Projected Precipitation Peak Flow Rate (cfs)
Total Allowable Discharge From the Site Total Allowable Discharge From the Site
2-year 0.15 0.05 0.36 0.12
10-year 1.40 0.58 2.35 1.45
100-year 5.89 5.81 10.24 10.09
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. Routing Diagram with Current and Projected Peak Flow Rates Superimposed [Figure: img-34.jpeg (original PDF, p. 80)](SOURCE.pdf#page=80) Source: HydroCAD® Diagram; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission. Each numbered element is called a "node." | Post-Construction Condition Off-Site Discharges | | | | | | --- | --- | --- | --- | --- | | Design Storm | Current Precipitation Peak Flow Rate (cfs) | | Projected Precipitation Peak Flow Rate (cfs) | | | | Total Allowable | Discharge From the Site | Total Allowable | Discharge From the Site | | 2-year | 0.15 | 0.05 | 0.36 | 0.12 | | 10-year | 1.40 | 0.58 | 2.35 | 1.45 | | 100-year | 5.89 | 5.81 | 10.24 | 10.09 | # Step 6: Demonstrate Compliance with the Groundwater Recharge Standards The design demonstrates that the increase in stormwater runoff volume from the pre-construction to the post-construction condition for the projected 2-year storm is infiltrated through the proposed SSGI bioretention BMPs and SSGI infiltration BMPs. The projected 2-year design storm, with a precipitation depth of 3.93 inches, will produce the pre- and post-construction condition runoff volumes noted below:

50. Table 50

BMP 2026, Ch 5, p. 81

Pre-construction Condition Post-construction Condition Increase
4,557 cf 22,443 cf 17,886 cf
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. | Pre-construction Condition | Post-construction Condition | Increase | | --- | --- | --- | | 4,557 cf | 22,443 cf | 17,886 cf | Each of the SSGI bioretention BMPs provides an infiltration volume of 939 cf (rounding up from 938.9) below the first orifice. Therefore, the SSGI infiltration basins have to provide a total of 16,008 cf, which means 8,004 cf in each BMP. Each SSGI infiltration BMP is designed with a footprint of 5,020 sf. With the bottom of the SSGI infiltration basin set at EL. 95.50, the lowest orifice of the basin is set at 1.60 ft above the bottom of the BMP, which places the orifice at EL. 97.10 in order to provide sufficient storage volume for the runoff to be infiltrated. A summary report from the modeling software of the proposed SSGI infiltration basin follows. Summary Report for the Projected 2-year Storm | Ex_5-8 NoExfiltration NOAA 24-hr C Proj_2yr Rainfall=3.93" | | | | | | | --- | --- | --- | --- | --- | --- | | Prepared by NJDEP | | | | | Printed 7/12/2023 | | HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC | | | | | Page 121 | | Summary for Pond 37P: SS Infiltration S | | | | | | | Inflow Area = 43,560 sf, 75.00% Impervious, Inflow Depth = 2.71" for Proj_2yr event | | | | | | | Inflow = 3.44 cfs @ 12.10 hrs, Volume= 9,825.2 cf | | | | | | | Outflow = 0.05 cfs @ 20.38 hrs, Volume= 1,648.9 cf, Atten= 99%, Lag= 496.9 min | | | | | | | Primary = 0.05 cfs @ 20.38 hrs, Volume= 1,648.9 cf | | | | | | | Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs | | | | | | | Peak Elev= 97.227 @ 20.38 hrs Surf.Area= 5,020 sf Storage= 8,670.1 cf | | | | | | | Plug-Flow detention time= 815.0 min calculated for 1,648.9 cf (17% of inflow) | | | | | | | Center-of-Mass det. time= 557.5 min (1,339.8 - 782.2) | | | | | | | Volume Invert Avail.Storage Storage Description | | | | | | | #1 95.500' 22,590.0 cf Custom Stage Data (Conic) Listed below (Recalc) | | | | | | | Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet) Wet.Area (sq-ft) | | | | | | | 95.500 5,020 0.0 0.0 5,020 | | | | | | | 96.500 5,020 5,020.0 5,020.0 5,271 | | | | | | | 97.100 5,020 3,012.0 8,032.0 5,422 | | | | | | | 97.500 5,020 2,008.0 10,040.0 5,522 | | | | | | | 98.500 5,020 5,020.0 15,060.0 5,773 | | | | | | | 99.500 5,020 5,020.0 20,080.0 6,025 | | | | | | | 100.000 5,020 2,510.0 22,590.0 6,150 | | | | | | | Device Routing Invert Outlet Devices | | | | | | | #1 Device 4 99.300' 20.0" long x 0.5" breadth Broad-Crested Rectangular Weir | | | | | | | Head (feet) 0.200 0.400 0.600 0.800 1.000 | | | | | | | Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | | | | | #2 Device 4 97.900' 12.0" W x 6.0" H Vert. Orifice/Grate C= 0.600 | | | | | | | #3 Device 4 97.100' 6.0" Vert. Orifice/Grate C= 0.600 | | | | | | | #4 Primary 95.500' 12.0" Round Culvert | | | | | | | L= 50.00' RCP, groove end projecting, Ke= 0.200 | | | | | | | Inlet / Outlet Invert= 95.500' / 95.000' S= 0.0100' /' Cc= 0.900 | | | | | | | n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf | | | | | | | Primary OutFlow Max=0.05 cfs @ 20.38 hrs HW=97.227" TW=94.000' (Dynamic Tailwater) | | | | | | | 4=Culvert (Passes 0.05 cfs of 4.58 cfs potential flow) | | | | | | | 1=Broad-Crested Rectangular Weir (Controls 0.00 cfs) | | | | | | | 2=Orifice/Grate (Controls 0.00 cfs) | | | | | | | 3=Orifice/Grate (Orifice Controls 0.05 cfs @ 1.21 fps) | | | | | |

51. Table 51

BMP 2026, Ch 5, p. 81

Ex_5-8 NoExfiltration NOAA 24-hr C Proj_2yr Rainfall=3.93"
Prepared by NJDEP Printed 7/12/2023
HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC Page 121
Summary for Pond 37P: SS Infiltration S
Inflow Area = 43,560 sf, 75.00% Impervious, Inflow Depth = 2.71" for Proj_2yr event
Inflow = 3.44 cfs @ 12.10 hrs, Volume= 9,825.2 cf
Outflow = 0.05 cfs @ 20.38 hrs, Volume= 1,648.9 cf, Atten= 99%, Lag= 496.9 min
Primary = 0.05 cfs @ 20.38 hrs, Volume= 1,648.9 cf
Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 97.227 @ 20.38 hrs Surf.Area= 5,020 sf Storage= 8,670.1 cf
Plug-Flow detention time= 815.0 min calculated for 1,648.9 cf (17% of inflow)
Center-of-Mass det. time= 557.5 min (1,339.8 - 782.2)
Volume Invert Avail.Storage Storage Description
#1 95.500' 22,590.0 cf Custom Stage Data (Conic) Listed below (Recalc)
Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet) Wet.Area (sq-ft)
95.500 5,020 0.0 0.0 5,020
96.500 5,020 5,020.0 5,020.0 5,271
97.100 5,020 3,012.0 8,032.0 5,422
97.500 5,020 2,008.0 10,040.0 5,522
98.500 5,020 5,020.0 15,060.0 5,773
99.500 5,020 5,020.0 20,080.0 6,025
100.000 5,020 2,510.0 22,590.0 6,150
Device Routing Invert Outlet Devices
#1 Device 4 99.300' 20.0" long x 0.5" breadth Broad-Crested Rectangular Weir
Head (feet) 0.200 0.400 0.600 0.800 1.000
Coef. (English) 2.80 2.92 3.08 3.30 3.32
#2 Device 4 97.900' 12.0" W x 6.0" H Vert. Orifice/Grate C= 0.600
#3 Device 4 97.100' 6.0" Vert. Orifice/Grate C= 0.600
#4 Primary 95.500' 12.0" Round Culvert
L= 50.00' RCP, groove end projecting, Ke= 0.200
Inlet / Outlet Invert= 95.500' / 95.000' S= 0.0100' /' Cc= 0.900
n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf
Primary OutFlow Max=0.05 cfs @ 20.38 hrs HW=97.227" TW=94.000' (Dynamic Tailwater)
4=Culvert (Passes 0.05 cfs of 4.58 cfs potential flow)
1=Broad-Crested Rectangular Weir (Controls 0.00 cfs)
2=Orifice/Grate (Controls 0.00 cfs)
3=Orifice/Grate (Orifice Controls 0.05 cfs @ 1.21 fps)
Source context and notes | Pre-construction Condition | Post-construction Condition | Increase | | --- | --- | --- | | 4,557 cf | 22,443 cf | 17,886 cf | Each of the SSGI bioretention BMPs provides an infiltration volume of 939 cf (rounding up from 938.9) below the first orifice. Therefore, the SSGI infiltration basins have to provide a total of 16,008 cf, which means 8,004 cf in each BMP. Each SSGI infiltration BMP is designed with a footprint of 5,020 sf. With the bottom of the SSGI infiltration basin set at EL. 95.50, the lowest orifice of the basin is set at 1.60 ft above the bottom of the BMP, which places the orifice at EL. 97.10 in order to provide sufficient storage volume for the runoff to be infiltrated. A summary report from the modeling software of the proposed SSGI infiltration basin follows. Summary Report for the Projected 2-year Storm | Ex_5-8 NoExfiltration NOAA 24-hr C Proj_2yr Rainfall=3.93" | | | | | | | --- | --- | --- | --- | --- | --- | | Prepared by NJDEP | | | | | Printed 7/12/2023 | | HydroCAD® 10.00-25 s/n 07311 © 2019 HydroCAD Software Solutions LLC | | | | | Page 121 | | Summary for Pond 37P: SS Infiltration S | | | | | | | Inflow Area = 43,560 sf, 75.00% Impervious, Inflow Depth = 2.71" for Proj_2yr event | | | | | | | Inflow = 3.44 cfs @ 12.10 hrs, Volume= 9,825.2 cf | | | | | | | Outflow = 0.05 cfs @ 20.38 hrs, Volume= 1,648.9 cf, Atten= 99%, Lag= 496.9 min | | | | | | | Primary = 0.05 cfs @ 20.38 hrs, Volume= 1,648.9 cf | | | | | | | Routing by Dyn-Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs | | | | | | | Peak Elev= 97.227 @ 20.38 hrs Surf.Area= 5,020 sf Storage= 8,670.1 cf | | | | | | | Plug-Flow detention time= 815.0 min calculated for 1,648.9 cf (17% of inflow) | | | | | | | Center-of-Mass det. time= 557.5 min (1,339.8 - 782.2) | | | | | | | Volume Invert Avail.Storage Storage Description | | | | | | | #1 95.500' 22,590.0 cf Custom Stage Data (Conic) Listed below (Recalc) | | | | | | | Elevation (feet) Surf.Area (sq-ft) Inc.Store (cubic-feet) Cum.Store (cubic-feet) Wet.Area (sq-ft) | | | | | | | 95.500 5,020 0.0 0.0 5,020 | | | | | | | 96.500 5,020 5,020.0 5,020.0 5,271 | | | | | | | 97.100 5,020 3,012.0 8,032.0 5,422 | | | | | | | 97.500 5,020 2,008.0 10,040.0 5,522 | | | | | | | 98.500 5,020 5,020.0 15,060.0 5,773 | | | | | | | 99.500 5,020 5,020.0 20,080.0 6,025 | | | | | | | 100.000 5,020 2,510.0 22,590.0 6,150 | | | | | | | Device Routing Invert Outlet Devices | | | | | | | #1 Device 4 99.300' 20.0" long x 0.5" breadth Broad-Crested Rectangular Weir | | | | | | | Head (feet) 0.200 0.400 0.600 0.800 1.000 | | | | | | | Coef. (English) 2.80 2.92 3.08 3.30 3.32 | | | | | | | #2 Device 4 97.900' 12.0" W x 6.0" H Vert. Orifice/Grate C= 0.600 | | | | | | | #3 Device 4 97.100' 6.0" Vert. Orifice/Grate C= 0.600 | | | | | | | #4 Primary 95.500' 12.0" Round Culvert | | | | | | | L= 50.00' RCP, groove end projecting, Ke= 0.200 | | | | | | | Inlet / Outlet Invert= 95.500' / 95.000' S= 0.0100' /' Cc= 0.900 | | | | | | | n= 0.011 Concrete pipe, straight & clean, Flow Area= 0.79 sf | | | | | | | Primary OutFlow Max=0.05 cfs @ 20.38 hrs HW=97.227" TW=94.000' (Dynamic Tailwater) | | | | | | | 4=Culvert (Passes 0.05 cfs of 4.58 cfs potential flow) | | | | | | | 1=Broad-Crested Rectangular Weir (Controls 0.00 cfs) | | | | | | | 2=Orifice/Grate (Controls 0.00 cfs) | | | | | | | 3=Orifice/Grate (Orifice Controls 0.05 cfs @ 1.21 fps) | | | | | | Source: HydroCAD® Summary Report; HydroCAD is a registered trademark of HydroCAD Software Solutions LLC. Used with permission.

52. Table 52

BMP 2026, Ch 5, p. 82

Input Values
1.00 R Recharge rate (permeability rate) (in/hr)
0.150 Sy Specific yield, Sy (dimensionless)
default value is 0.15; max value is 0.2 provided that a lab test data is submitted
1.00 Kh Horizontal hydraulic conductivity (in/hr)
Kh = 5xRecharge Rate (R) in the costal plan; Kh=R outside the coastal plan
20.000 x 1/2 length of basin (x direction, in feet)
11.875 y 1/2 width of basin (y direction, in feet)
11.86 t Duration of infiltration period (hours)
10.00 hi(0) Initial thickness of saturated zone (feet)
15.222 h(max) Maximum thickness of saturated zone (beneath center of basin at end of infiltration period)
9.222 Δh(max) Maximum groundwater mounding (beneath center of basin at end of infiltration period)
Source context and notes - ½ of the BMP width = 11.875 ft (half of the width) The duration of infiltration period is equal to the volume of infiltrated runoff divided by the product of the BMP footprint and the recharge rate, and the calculation includes a conversion factor for converting inches to feet. ## Duration of Infiltration Period = 11.86 hour = $$\frac{939\ cf}{\left[950\ sf\ x\left(1\frac{in}{hr}\ x\ \frac{1\ ft}{12\ in}\right)\right]}$$ | Input Values | | | | | | | | | | --- | --- | --- | --- | --- | --- | --- | --- | --- | | 1.00 | R | Recharge rate (permeability rate) (in/hr) | | | | | | | | 0.150 | Sy | Specific yield, Sy (dimensionless) | | | | | | | | | | default value is 0.15; max value is 0.2 provided that a lab test data is submitted | | | | | | | | 1.00 | Kh | Horizontal hydraulic conductivity (in/hr) | | | | | | | | | | Kh = 5xRecharge Rate (R) in the costal plan; Kh=R outside the coastal plan | | | | | | | | 20.000 | x | 1/2 length of basin (x direction, in feet) | | | | | | | | 11.875 | y | 1/2 width of basin (y direction, in feet) | | | | | | | | 11.86 | t | Duration of infiltration period (hours) | | | | | | | | 10.00 | hi(0) | Initial thickness of saturated zone (feet) | | | | | | | | | | | | | | | | | | 15.222 | h(max) | Maximum thickness of saturated zone (beneath center of basin at end of infiltration period) | | | | | | | | 9.222 | Δh(max) | Maximum groundwater mounding (beneath center of basin at end of infiltration period) | | | | | | | The results in the above graphic taken from the Hantush Spreadsheet show the groundwater mounding height is 5.222 ft above the seasonal high water table (SHWT). Given the condition that the existing grade at the location of the SSGI bioretention BMP is at EL. 103.00 and that the SHWT is located 13 ft below the basin bottom (basin invert), the top of the groundwater mounding is at EL. 95.222 (EL. 103.00 - 13 ft + 5.222 ft). Therefore, the mounding in the

53. Table 53

BMP 2026, Ch 5, p. 83

Input Values
1.00 R Recharge rate (permeability rate) (in/hr)
0.150 Sy Specific yield, Sy (dimensionless)
default value is 0.15; max value is 0.2 provided that a lab test data is submitted
1.00 Kh Horizontal hydraulic conductivity (in/hr)
Kh = 5xRecharge Rate (R) in the coastal plain: Kh=R outside the coastal plain
62.750 x 1/2 length of basin (x direction, in feet)
20.000 y 1/2 width of basin (y direction, in feet)
19.20 t Duration of infiltration period (hours)
10.00 hi(0) Initial thickness of saturated zone (feet)
19.464 h(max) Maximum thickness of saturated zone (beneath center of basin at end of infiltration period)
9.464 Δh(max) Maximum groundwater mounding (beneath center of basin at end of infiltration period)
Source context and notes Horizontal hydraulic conductivity = 1 inch/hour (outside the coastal plan) $\frac{1}{2}$ of the BMP length = 62.75 ft (half of the length) $\frac{1}{2}$ of the BMP width = 20.00 ft (half of the length) Duration of infiltration period = 19.2 hour = $\frac{8,032\ cf}{\left[5,020\ sf\ x\left(1\frac{in}{hr}x\ \frac{1ft}{12in}\right)\right]}$ | Input Values | | | | | | | | | | | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | | 1.00 | R | Recharge rate (permeability rate) (in/hr) | | | | | | | | | 0.150 | Sy | Specific yield, Sy (dimensionless)
default value is 0.15; max value is 0.2 provided that a lab test data is submitted | | | | | | | | | 1.00 | Kh | Horizontal hydraulic conductivity (in/hr)
Kh = 5xRecharge Rate (R) in the coastal plain: Kh=R outside the coastal plain | | | | | | | | | 62.750 | x | 1/2 length of basin (x direction, in feet) | | | | | | | | | 20.000 | y | 1/2 width of basin (y direction, in feet) | | | | | | | | | 19.20 | t | Duration of infiltration period (hours) | | | | | | | | | 10.00 | hi(0) | Initial thickness of saturated zone (feet) | | | | | | | | | 19.464 | h(max) | Maximum thickness of saturated zone (beneath center of basin at end of infiltration period) | | | | | | | | | 9.464 | Δh(max) | Maximum groundwater mounding (beneath center of basin at end of infiltration period) | | | | | | | | The result shows that the mounding height is 9.46 ft above the SHWT, which places the mounding height at EL. 97.46. However, the bottom surface of the BMP is at EL. 96.0. The mounding of the groundwater table caused by the proposed BMP will therefore affect the infiltration of the runoff. The next step is to adjust the duration of infiltration period and proportionally reduce the recharge rate. Increasing the duration of infiltration period to be 72 hours will require the recharge rate be proportionally reduced to 0.27 inches/hour. The mounding height becomes 6.97 ft, which is at EL. 94.97. The mounding analysis demonstrates that a mounding in the groundwater table caused by the proposed infiltration of runoff is below the bottom surface of the BMP at EL. 96.0 when the duration of infiltration is extended to 72 hours. Since the

54. Table 54

BMP 2026, Ch 5, p. 84

Input Values
0.27 R Recharge rate (permeability rate) (in/hr)
0.150 Sy Specific yield, Sy (dimensionless) default value is 0.15; max value is 0.2 provided that a lab test data is submitted
1.00 Kh Horizontal hydraulic conductivity (in/hr) Kh = 5xRecharge Rate (R) in the coastal plain: Kh=R outside the coastal plain
62.750 x 1/2 length of basin (x direction, in feet)
20.000 y 1/2 width of basin (y direction, in feet)
72.00 t Duration of infiltration period (hours)
10.00 hi(0) Initial thickness of saturated zone (feet)
16.967 h(max) Maximum thickness of saturated zone (beneath center of basin at end of infiltration period)
6.967 Δh(max) Maximum groundwater mounding (beneath center of basin at end of infiltration period)
Source context and notes # Stormwater Management Quantity and Quality Standards and Computations Source revision: January 2026. duration of infiltration is within the maximum drain downtime of 72 hours, the result of the mounding analysis is acceptable. | Input Values | | | | | | | --- | --- | --- | --- | --- | --- | | 0.27 | R | Recharge rate (permeability rate) (in/hr) | | | | | 0.150 | Sy | Specific yield, Sy (dimensionless) default value is 0.15; max value is 0.2 provided that a lab test data is submitted | | | | | 1.00 | Kh | Horizontal hydraulic conductivity (in/hr) Kh = 5xRecharge Rate (R) in the coastal plain: Kh=R outside the coastal plain | | | | | 62.750 | x | 1/2 length of basin (x direction, in feet) | | | | | 20.000 | y | 1/2 width of basin (y direction, in feet) | | | | | 72.00 | t | Duration of infiltration period (hours) | | | | | 10.00 | hi(0) | Initial thickness of saturated zone (feet) | | | | | | | | | | | | 16.967 | h(max) | Maximum thickness of saturated zone (beneath center of basin at end of infiltration period) | | | | | 6.967 | Δh(max) | Maximum groundwater mounding (beneath center of basin at end of infiltration period) | | | | The above calculations and designs show how to use the current precipitation depth and the projected precipitation depth to demonstrate compliance with the Stormwater Management rules. # Example 5-9: Calculate the Peak Flow Rate for Sizing a Manufactured Treatment Device Treating the WQDS from a 0.25-acre Impervious Motor Vehicle Surface The following parameters apply for a site located in Mercer County:

55. Table 5-4: Summary of Modeling Guidance for Various Site Conditions

BMP 2026, Ch 5, p. 85

Site Condition or Parameter NRCS Methodology
Applicability Peak flow rate, runoff volume, hydrograph comparison, sizing inflow rate and volume of BMPs
Groundwater Recharge Difference of Runoff volumes of pre- and post-construction projected 2-year storms
Mixture of pervious and directly connected impervious surfaces Calculate the runoff from impervious surface and pervious surface separately
Unconnected impervious surface NEH Part 630, Chapter 9 unconnected impervious surface (less than 30%) or NJ DEP Two-Step Technique
Runoff Parameters Curve Numbers from NEH, Part 630, Chapter 9
Rainfall Data Use either NOAA precipitation data or NRCS County average rainfall data, as follows:
- Apply current precipitation adjustment factors to the rainfall data for the current design storms for both the pre- and post-construction conditions
- Apply future precipitation change factors to the rainfall data and calculate the projected precipitation depths for the projected design storms for both the pre- and post-construction conditions NJDEP Water Quality Design Storm rainfall is 1.25 inches in 2 hours
Pre-construction Time of Concentration Assume sheet flow length = 100 ft, unless a physical condition exists that shortens the sheet flow length to less than 100 ft
Maximum sheet flow roughness coefficient n = 0.40
Post-construction Time of Concentration There is no minimum value for T_{c}
An assumed T_{c} value may not be used
Maximum Sheet flow length is 100 feet or the length calculated by McCuen-Spiess limitation, whichever is smaller
Maximum sheet flow roughness coefficient n = 0.40
Source context and notes Source revision: January 2026. # Guidance Summary The following table summarizes how the methods discussed in this chapter may be used to meet the various requirements established in N.J.A.C. 7:8. Table 5-4: Summary of Modeling Guidance for Various Site Conditions | Site Condition or Parameter | NRCS Methodology | | --- | --- | | Applicability | Peak flow rate, runoff volume, hydrograph comparison, sizing inflow rate and volume of BMPs | | Groundwater Recharge | Difference of Runoff volumes of pre- and post-construction projected 2-year storms | | Mixture of pervious and directly connected impervious surfaces | Calculate the runoff from impervious surface and pervious surface separately | | Unconnected impervious surface | NEH Part 630, Chapter 9 unconnected impervious surface (less than 30%) or NJ DEP Two-Step Technique | | Runoff Parameters | Curve Numbers from NEH, Part 630, Chapter 9 | | Rainfall Data | Use either NOAA precipitation data or NRCS County average rainfall data, as follows:
- Apply current precipitation adjustment factors to the rainfall data for the current design storms for both the pre- and post-construction conditions
- Apply future precipitation change factors to the rainfall data and calculate the projected precipitation depths for the projected design storms for both the pre- and post-construction conditions NJDEP Water Quality Design Storm rainfall is 1.25 inches in 2 hours | | Pre-construction Time of Concentration | Assume sheet flow length = 100 ft, unless a physical condition exists that shortens the sheet flow length to less than 100 ft
Maximum sheet flow roughness coefficient n = 0.40 | | Post-construction Time of Concentration | There is no minimum value for T_{c}
An assumed T_{c} value may not be used
Maximum Sheet flow length is 100 feet or the length calculated by McCuen-Spiess limitation, whichever is smaller
Maximum sheet flow roughness coefficient n = 0.40 |

Images on table pages